## The site diary: what the law says. What you need to know under DM 49/2018

Did you know that, by law, the site diary must be digital? No problem with Mela: the easiest and fastest solution, in compliance with the D.M.

The site diary: what the law says and what you need to know under DM 49/2018

The site diary: what the law says



The site diary: what the law says. The site diary is the document in which everything that happens on a construction site is recorded, and which includes all the people involved in various capacities in delivering a project. It is the accounting document used to **monitor site activity**, day by day, from both a **technical** and **financial** perspective.



The site diary is fundamental to contract management and work on site, and above all answers two questions:



### a. Does my work meet the requirements of Italian legislation?



The site diary is a document for managing the execution of works, applying the requirements imposed by law in relation to carrying out the works.



### b. How can I avoid problems, or worse, disputes?



The site diary provides a step-by-step record of what happens on site, helping to resolve any doubts about the correct execution of the works or disputes that may arise between the client, works director and contractor. Not only that: **the site diary limits execution errors and reduces the risk of financial damage to the public purse**, for which the works director could be held liable if the project has objective discrepancies from the one initially approved.

The site diary: what the law says

***[Click here for more information](http://ec2-18-197-228-208.eu-central-1.compute.amazonaws.com/it/support)***



### Who is responsible for the site diary?



The administrative and accounting officer is the **works director**, whose task is to complete the accounting documents accurately and promptly, check whether the works have been carried out correctly, and add observations, instructions and warnings. They must then sign them. Accounting documents, it should be remembered, are public records for all legal purposes, used to ascertain and record events that generate expenditure. The works director is **appointed by the contracting company (the client) on the proposal of the Sole Procedure Manager (Responsabile Unico del Procedimento, RUP)**, and must have suitable professional qualifications and expertise, in accordance with the contract established.



### The site diary: DM 49/2018



**Article 14** of the [new decree on works supervision – dm 49/2018](https://www.gazzettaufficiale.it/eli/gu/2018/05/15/111/sg/pdf) sets out even more precisely **the elements to be recorded daily** in the site diary:



1. **The order, method and activity** by which the works progress
2. **The qualifications and number of workers** employed
3. **The technical equipment used** to carry out the works
4. **The list of supplies** provided by the contractor, documented by settled invoices, and everything relating to the **technical and financial progress** of the works, including any accidents
5. Circumstances and events that may affect the works, such as weather or **hydrometric** readings, or information about the nature of the ground
6. Service instructions and **service orders from the RUP** (Responsabile Unico del Procedimento, Sole Procedure Manager) and the works director
7. **Reports addressed to the RUP**
8. **Records of fact-finding activities** or tests
9. **Disputes, suspensions and resumptions** of the works
10. Properly ordered **variations**, and **changes or additions to prices**



The arrangements for maintaining this document, its responsibilities and its contents are essential to a full understanding of the execution of the project, both for the works director and the contractor.



### By law, the site diary must be a digital document



That’s right: **digitalisation is the key word** in the new provisions. According to **Article 15 of dm 49/2018**, “Work accounting is carried out using specific electronic tools that use platforms, including online platforms.” These electronic tools must be able to guarantee:



1. **AUTHENTICITY**, together with **transparency and simplification**
2. **SECURITY** of the data entered
3. **Provenance** of the data from the **COMPETENT PARTIES**



### Mela is the answer, in full compliance with D.M. 49/2018



For your site diary, Mela is a mobile and web application that works like a chat and **fully complies with the requirements of D.M. 49/2018** (Guidelines on works supervision).



[Very simple to use](/en/product/construction-daily-log) - it requires no specialist skills or training to learn, and allows you to document, **day after day with your smartphone, what happens on site**: with text messages, signatures, photos, voice messages, videos and uploaded records.



With Mela, you can easily track people, materials and services on a single platform, using your smartphone and connecting it with other devices such as computers and tablets. You can also **create your printable site diary quickly, with one click and no additional work**. The report produced in this way **guarantees the authenticity and security** of the data and parties, as **required by law**.



## Mela can therefore fully have “legal value”



With Mela, you can create a fully secure digital “[site diary](/en/blog/construction-logbook-completed-example)” in accordance with current legislation. Mela is not only an IT tool capable of making processes more efficient, but **also guarantees the full legal compliance of the processes** themselves.



## The site diary: what the law says. Update September 2022



With Mela, the Site Diary is automatically generated from notes, photos, videos and transcriptions of voice notes; it can be signed by all the parties involved and will be **[notarised on blockchain](/en/blog/construction-blockchain-report-notarization)**. It thus becomes a certified document that can be relied on in court\!



[All photos, videos, screenshots, documents and audio files are certified](/en/blog/certified-construction-photos-italian-tax-credit-transfer) in Mela, guaranteeing the authenticity and unalterability of every item captured. Mela’s [certified photos](/en/blog/useful-apps-for-construction-sites-taking-and-sharing-pictures) are also valid for the transfer of credit for [Superbonus 100%](/en/blog/italian-superbonus-110-ten-steps), as required by the **[Circular 23/E](https://www.agenziaentrate.gov.it/portale/documents/20143/4495900/Circolare+Superbonus++23.06.2022.pdf/e7a29cee-4864-5dcb-b335-aa21518d0ea1)** of the Italian Revenue Agency dated 23 June 2022.

Construction site management software: photos

## Is the Site Diary therefore compulsory by law?



In summary, the obligation to establish a construction site Site Diary is set out in **two regulations:**



- The Ministerial Decree of 7 March 2018, no. 49, which makes it compulsory for works falling within the scope of public contracts;


- The [Decree of 6 June 2001, no. 380,](https://www.gazzettaufficiale.it/eli/id/2001/11/15/01A12340/sg) which makes it compulsory **also for works** that do not fall within public procurement contracts.



## Questions and answers



**1. What is the Site Diary?**



The Site Diary is the construction-site document in which everything that happens on site is recorded and which includes all the people involved in delivering a project. It is the accounting document used to monitor site activity day by day, and is compulsory by law.



\*\*2. Who must complete the Site Diary?
\*\*



The [Works Director](/en/blog/the-role-of-the-project-director) is responsible for completing the Site Diary. Their task is to update the document accurately and promptly and sign it to certify the proper completion of the [SAL](/en/blog/work-in-progress-reports) - Stato Avanzamento Lavori (Work Progress Status).



**3. What must be recorded in the Site Diary?**



Article 14 of the [new decree on works supervision – dm 49/2018](https://www.gazzettaufficiale.it/eli/gu/2018/05/15/111/sg/pdf) sets out very precisely what must be recorded daily in the site diary. The elements to be recorded include: the order, method and activity by which the works progress, the qualifications and number of workers employed, and the equipment used to carry out the works.