Discover the documents, checks and digital tools that make construction site accounting more precise, transparent and timely for public contracts.

## Public procurement site accounting: here are the right tools

Public procurement site accounting: we are in 2021, and approximate figures are no longer acceptable. Inaccuracy comes at a high price, with extra, unbudgeted costs that could easily be avoided. So what should site accounting look like on a public contract? It should be carried out using the right digital tools: high-performing tools designed around the needs of people working on site every day.

Public procurement site accounting: the right tools

App for work reports



Cost analysis and accounting are crucial aspects of site management because, if we do not keep a timely record of what we are spending, we will only know [the costs days or weeks later](/en/blog/non-digital-construction-cost-management) and will therefore be able to take corrective action only after a delay, when the work has moved on to a subsequent stage\!



A failure to control costs promptly means **being unable to make informed, well-founded decisions**, uncontrollably increasing project risks **with two consequences**:



- **We will be unable to prioritise** the work correctly, increasing the final risks for the community


- **We will pay in money and time for improvised variations** and unplanned work



> Site accounting must therefore be monitored using modern tools and with the help of digital technology.



Let us examine the accounting procedures and documents required or recommended by Italian legislation ([DM 49/2018](/en/blog/italy-ministerial-decree-49-2018-site-compliance)).



## Who checks site accounting? The RUP (sole person responsible for the procedure)



First of all, the person responsible for the works must analyse **site accounting**, which establishes the contract price based on the completed works and the contract between the contracting authority and the contractor.



The subsequent work stages **must comply with the timescales** and site costs established by the contract. It is essential that the person responsible always keeps **costs and work progress under review**: this is where site management and accounting tools come into play. They also make it possible to digitalise these processes simply.



## Public procurement site accounting: the measurement book for works and supplies



Listed among the accounting records in Art. 14 of DM 49/2018, the “Measurement Book for Works and Supplies” is the accounting document that makes it possible to **verify the quantity of work completed** by measuring and classifying the works carried out over time.



The works director is responsible for measuring the work. On each site visit, they record the measurements in the measurement book and indicate the quantities completed.



The measurement book must be a document **jointly reviewed by the Technical Director, contractor and contracting authority**: what was done and how much was done cannot be subjective\!



Digital tools make it possible to create an environment in which the 3 parties **access a single set of data and check its accuracy**. Reservations, comments and discussions are tracked **with complete transparency**.

Public procurement site accounting

## How do you carry out site accounting? With the works log



The works log is the key site document, allowing the technical and financial progress of a project to be checked day by day.



The works director is responsible for the accounting control of **everything carried out during the works** through the [works log](/en/blog/construction-logbook-completed-example).



In theory, the site log describes **the number of workers and the hours worked by each of them to carry out a project**, the materials brought onto the site, the equipment required and owned by the company or supplied by third parties, any accidents and any variations to the works, with the resulting changes to prices.



Today, we need to evolve digitally\! The data collected above was used to **ensure traceability and transparency** in a predominantly paper-based world. Today, the works log cannot do without numerous photos, videos and reports that emulate the business intelligence of management systems. The **measurement book** is part of this too—not as a table anymore, but as a dashboard\!



> What should you write in the works log?



[Here you will find an effective summary\>\>](/en/blog/fill-construction-logbook-four-key-points)



## Site accounting: the accounting register and summary



DM 49/2018 established that an **accounting register** may also be present, covering **the complete accounting of the project**.



The legislator states that expenditure relating to work progress is recorded in the **summary**, which records **the quantity of each completed work item and its corresponding costs**, to verify whether they match the accounting register.



In short, if we want to translate this way of thinking into contemporary graphics, we need to use **pie charts for the summary and bar charts for the accounting register**. The tables behind these charts can no longer be Excel spreadsheets because, as mentioned above, business intelligence must be shared.



## Public procurement site accounting: what is the state of progress of works (SAL)?



The **[state of progress of works SAL](/en/blog/work-in-progress-reports)** is the document that certifies **all the work carried out from the start of the contract to the end of the project**, so that the amount payable by the client to the appointed company for carrying out the work can be calculated.



The works director is responsible for **checking the costs associated with carrying out the project or works**, completing the accounting documents promptly and accurately. It should be remembered that accounting documents, as also confirmed by DM 49/2018, are public acts for all legal purposes.



## What is the final account for the works?



The final account for the works **defines** precisely and definitively, once the works are complete, the amount due to the contractor and any credit balance. It is an accounting document issued by the works director, always accompanied by the **report on the final account**.



The latter establishes the **proper completion of the project**, confirming that its form, dimensions, quantities, quality and supply of materials are **compliant with the contract** signed between the contracting authority and the company.



The various SALs and the final account are essentially **records certifying the data collected up to that point**. They represent a point of contact and, especially in the past, discussion.



In fact, **creating shared digital spaces where data is unique**—the measurement book, works log and accounting register—and **monitored** over time, without delays in accessing the data, **drastically reduces project-closing problems**, benefiting the entire ecosystem.



> This is essential when we consider the public investments we need to make in the coming years for the Recovery Fund, Recovery lan and Next Generation EU

Public procurement site accounting

## Mela for site accounting: a valuable ally\!



Site accounting, across the range of accounting documents we have examined, is a precise and timely record of **what has been completed and how it was completed**.



It is clear that accounting is closely linked to site supervision and control, ensuring that everything takes place within the established terms and minimising the site's presumed unpredictability and margin of error.



The tools we recommend for accounting are above all **digital and mobile**—because bulky, non-portable objects have no place on a construction site—and characterised by **ease of use**, designed first for field work and then for office work.



Finally, they can **collect data directly on site** and **present it immediately to all the parties involved**.



With the Mela app, you can digitalise the works log, measurement book and accounting register based on the project's bill of quantities and integrate them as needed.



This will allow you to **check project accounting promptly and accurately**, bringing major benefits to your site's productivity and reducing costs caused by inefficiency and delays.