Learn what a site handover report must contain, who prepares and signs it, and how it records the start of construction or renovation works.

## Site handover report: what it must contain in 2023

Site handover report: what it is, why it is fundamentally important, and who is responsible for preparing and signing it. What this document, which has legal value in every respect, must contain.

Site handover report: what it must contain in 2023

Site handover report under DM 49/2018



The site handover report is a document that marks the start of the works and signals the transition **from the [design phase](/en/blog/the-construction-project) to the execution phase.**



The site handover report establishes when the contractor temporarily takes possession of the property or building work in order to carry out construction or renovation works.



It is therefore clear why the site handover report, prepared and signed by the parties, is of fundamental importance: **it marks the beginning of a series of legal acts and operations** through which the contractor takes charge, for the period stipulated in the [works contract](/en/blog/tender-documentation-digital-example), of the area or building where the works are to be carried out.



> Which professional is responsible for the site handover report? Who must prepare it, and what must it necessarily contain?



## Site handover report: how does it take place?



The handover of the works is an important step because it allows the company that won the contract to actually begin work. It is essential to understand **how and when it takes place** so that everything is done correctly, both for the contractor and for the contracting authority.



On the agreed day for the joint [site inspection](/en/blog/site-inspection-report-what-it-is) and handover of the works, the works director will prepare a site handover report. This document is very important and a priority because it contains all the information needed to start the works correctly.



## Site handover report: one point is truly fundamental



As with the [site diary](/en/blog/construction-logbook-who-completes-it-2023) or the [progress report](/en/blog/italian-work-progress-sal-preparation-2023), responsibility for completing the site handover report lies with the works director, who must carefully verify and then record with the utmost precision all the information and findings established jointly by the parties.



But one point is fundamental above all, especially from a legal perspective, for the site handover report: **the agreed date,** from which all the protections established in the works contract take effect.



If it has been established that the works must last for a specified number of days or weeks, and that handover of the property or structure must take place by that date, the planned schedule must be respected. Otherwise, the contractor that delayed the works will be required to pay a penalty for each day of delay in relation to the report.



> When the contractor gains control of the property where it must carry out the works agreed in the works contract and specified in the annexes, everything will be ready for the works to begin.

Site handover report

## [](/en/blog/construction-blockchain-report-notarization)Site handover report: what must be checked



What elements must be checked during the handover of the works?



- First of all, the **condition of the work area** - check whether the area corresponds to the project indications and the surveys carried out, ensuring that there are no differences between the actual conditions and the design specifications.


- **Correspondence** between the design indications and the presence of utility networks, roads, areas of historical, artistic or archaeological interest, or other properties in or near the work area.


- **Accessibility of the area** and whether all its parts can be reached - check that the area is free from people or objects that could prevent or obstruct the works.


- **Any existing features** and how to manage them, with the necessary considerations to ensure the works are carried out correctly.


- The **status of the authorisations** required to carry out the works and any requirements that must be fulfilled.



These elements will be recorded in the report prepared and signed during the joint checks.



## The essential elements to include in the handover report



What are the **essential elements** that the works director should include in the site handover report to establish a clear record and ensure proper documentation? We have identified 12:



1. The **contractually specified number of days** for completing the works
2. The day, month and year from which the periods established by the contract begin
3. The names and respective roles of those present at the handover of the works
4. The **authorisation from the RUP** to hand over the works by means of a written notice: without this, it will not be possible to proceed with the handover of the works
5. The details of the planning permission for carrying out the work
6. The **seismic authorisations** required for carrying out the work
7. The **prior notification**, where required under Article 99 of Italian Legislative Decree (D Lgs) 81/08
8. A declaration that the area where the works are to be carried out is **free from people and objects**, and that its current condition does not prevent the works from starting and continuing.
9. The works director’s **acknowledgement** of the explanations concerning the works to be carried out, including an indication of existing interfaces
10. The contractor’s legal representative’s acknowledgement that the works can begin immediately
11. The recognised local **special conditions and circumstances**, and the operations carried out, such as setting out, measurement checks, and positioning profiles and benchmarks
12. Details of the areas, premises, location and capacity of the quarries and tips made available or allocated to the appointed contractor, together with the **equipment and machinery** for carrying out the works

Site handover report

## With Mela, site handover reports can be completed and signed using a smartphone



With the [Mela construction site app](/en), you can create your own report template, complete it directly on your smartphone and have everyone sign it directly in the chat. And that’s not all\!



### Mela uses blockchain for site handover reports



Mela uses the **immutability and transparency** of [Blockchain technology](/en/blog/construction-blockchain-report-notarization) to save and manage site handover reports, making them visible and verifiable by all the parties involved or by third parties, such as a lawyer.
For the [Works Director](/en/blog/construction-project-director-report-templates), blockchain provides an **additional guarantee that reports can be verified and remain immutable**. They can be saved and shared with the contractor or the end client on distributed ledgers.

## Article video

## Questions and answers



**What is a site handover report?**



A site handover report is a document that establishes when the contractor **temporarily takes possession of the property** or building work in order to **carry out construction or renovation works**. In practice, the site handover report marks the transition from the design phase to the phase in which the works begin.



**Who completes the site handover report?**



The works director is responsible for preparing the site handover report and must also have all the project stakeholders sign it, including the contractor and the contracting authority.



**Why is the site handover report important?**



The site handover report is fundamentally important because **it marks the beginning of a series of legal acts and operations** through which the contractor takes charge, for the period specified in the works contract, of the area or building where the works are to be carried out.