## What is the Setting-Out and Works Commencement Record? Requirements. Parties. Template.

We provide a summary, for ease of understanding, of the setting-out and works commencement record for construction projects, a mandatory requirement in the sector, and make it easier to complete correctly through a Mela template for the various building professionals regulated by Spain’s Act on Building Regulation (Ley de Ordenación de la Edificación, LOE) 38/1999.

Setting-out and works commencement record: requirements, parties and template

Setting-Out and Works Commencement Record: Requirements, Parties and Template



**CONTENTS:**



1. 
2. 
3. 
4. 
5. 



## 



**1. Introduction**



In a previous article, we discussed the [Building Handover Record (for a completed building)](/en/blog/completed-building-acceptance-report-spain), which—like the **setting-out and works commencement record**—is governed by Spain’s Act on Building Regulation (Ley de Ordenación de la Edificación, LOE) [(LOE) 38/1999](https://www.boe.es/eli/es/l/1999/11/05/38/con). As its name suggests, the **setting-out and works commencement record** includes, on the one hand, the setting-out process (various technical matters, such as the plans and dimensions of the plot where the building is constructed, as well as the materials to be used) and, for all purposes, also serves as confirmation and consent by all the parties involved in the building process, who ratify the date on which the works begin.



It is important to clarify that, if unforeseen events or simply circumstances requiring the terms under which the record was signed to be amended arise during the management of the works, the consent of the parties is sufficient to update or amend it. It should therefore be understood that it records the conditions at the time the works begin.



## 



**2. What requirements must the setting-out and works commencement record meet?**

What requirements must the setting-out and works commencement record meet

To give the document consistency and validity, it must include at least the following information:



1. Name of the project, address / location and municipality.
2. Confirmation that an execution project exists corresponding to the works licence. The file number and date of issue must be recorded.
3. The name of the site manager appointed by the contractor, in accordance with the requirements of the aforementioned Spanish Act on Building Regulation (Ley de Ordenación de la Edificación, LOE) 38/1999 in Article 11.
4. Approval by the Health and Safety Coordinator of the relevant plan, adapted to the project and the characteristics of the works.
5. Confirmation that the contractor has verified that the project fits within the plot boundary through the setting-out process, and that this verification has been endorsed by the Works Execution Director and the Works Director.
6. The contractor’s readiness to begin the works on the date recorded in the document.
7. The names of the Developer, the Project Authors and the Contractor or Contractors.



## 



**3. Which parties** **involved in the building process must sign the** **setting-out and works commencement record?**



- Works Director or Directors.


- Works Execution Director or Directors.


- The Health and Safety Coordinator during execution.(\*)


- The Contractor.



**(\*)Although this is not expressly required by Spain’s Act on Building Regulation (Ley de Ordenación de la Edificación, LOE), experience recommends including them. It should be remembered that the professions qualified to perform this function are architect, technical architect, engineer or technical engineer, “in accordance with their competences and skills”.**



## 



**4. What does Mela offer for editing, completing, signing and sharing the setting-out and works commencement record?**

What does Mela offer for editing, completing, signing and sharing the setting-out and works commencement record

To make completion and sending easier, provide flexibility when adapting the document to the client and comply with the required legal requirements, **Mela** offers you a **template** for the **setting-out and works commencement record**. From this template, you can **easily and intuitively adapt it**, link it to a project and **store** it so that you can quickly and easily **locate it** later. You can also **sign it from within the application**, both yourself and the parties involved, and share it with anyone you consider necessary.



In the following video, we explain how to manage, modify and sign this document and any other template you have added to [Mela](/en).

## Article video

## 



**5. Conclusions**



As required by law, both the beginning and the end of the works must be recorded in documents setting out the terms and agreements between the parties involved in the building process. These terms are established in Spain’s Act on Building Regulation (Ley de Ordenación de la Edificación, LOE) [(LOE) 38/1999](https://www.boe.es/eli/es/l/1999/11/05/38/con).



Simplifying and digitally storing documentation associated with works, together with the ease of sharing it—and the resulting savings in time spent searching for it, paper, ink and physical attendance, since it can be signed from within the application—is a trend in construction project management applications and another way to help improve your company’s efficiency.



The Mela application, a digital site diary and cost-control tool for builders and installers, makes it easy: an editable **setting-out and works commencement record** template, signing on site, easy sharing, even outside the application itself, and secure cloud storage, so you will save space on your mobile phone.