How to prepare the Building Handover Certificate (for a completed building): examples and guide
Learn how to prepare, complete, sign and share a building handover certificate, with its legal requirements and a practical digital template from Mela.
The Handover Certificate is a legally required document that guarantees, for both the developer and the client, compliance with the agreements made before the works began. We summarise its content and requirements and explain how to use the template, which you can sign even on site.
Building Handover Certificate for a completed building
What is a Building Handover Certificate and why is it important in the construction sector?
Efficient process management in any industry is a differentiating factor that also makes its participants more competitive. Logically, the construction sector is one of those industries. Recent advances, such as the widespread use of augmented reality and the digitalisation of processes, among others, help achieve this efficiency.
In this article, we explain how to use Mela to digitalise, store, share and send one of the essential documents in every construction project or works: the Building Handover Certificate for a completed building, easily, quickly and efficiently using digital tools and templates. This saves time, as you only need to enter the details of each project.
The Building Handover Certificate for completed works is an important legal document that officially certifies the partial or total handover of the works to the developer (or client) by the contractor. Total or partial handover results from the prior agreement between the parties; in other words, the same project or works may have several Handover Certificates or just one.
The Building Handover Certificate for completed works is regulated by Spanish Law 38/1999, of 5 November, on “Ley de Ordenación de la Edificación” (Building Regulations Act), published in Spain’s Official State Gazette. This law sets out the obligations, requirements, content and commitments assumed by the parties signing the Certificate.
We highlight these two aspects of its importance in the construction sector:
a) “Unless expressly agreed otherwise, handover of the works shall take place within thirty days of the date of completion, evidenced by the final certificate of works, with this period beginning from the written notification sent to the developer”.
b) “The calculation of the liability and guarantee periods established in this Law shall begin on the date on which the handover certificate is signed, or when handover is deemed to have taken place implicitly as provided for.”
Regarding point a), it is important to note that the date of the Building Handover Certificate is crucial because, for all purposes, it is the starting date for calculating the period available to the client or developer to make the relevant claims, as well as for the contractor to issue the final Certificate of Works (30 calendar days after the certificate is signed). This certificate is issued when there are no claims from the developer (without reservations), either because this is stated in writing or because no objection is raised.
The developer may partially accept the Certificate, leaving remedial work or corrections by the contractor outstanding (this is what is known as acceptance with reservations). Details of these claims and the deadline for remedying them must be included in the Certificate.
Contents of the Handover Certificate. Requirements.
In accordance with Spanish Law 38/1999 on “Ley de Ordenación de la Edificación” (Building Regulations Act), which, despite its age, was reviewed in June 2022 and whose latest version is the one we are working with, the Certificate must, at a minimum, have the following features to be legally fully valid and provide all guarantees for both parties:
a) It must be signed by the developer and the contractor.
b) It must include the date of the final certificate for the entire works or for the completed and finished phase (partial handover).
c) It must state the final cost of the material execution of the works (including labour costs).
d) It must objectively state whether the developer has identified defects or non-conformities, as well as the deadlines for the contractor to remedy them.
e) It must specify any guarantees that may, where applicable, be required from the contractor to ensure fulfilment of its responsibilities.
A practical example: many of us have experienced, or have a family member or friend who has experienced, buying a new flat in a newly built development. After moving into the new flat, it is possible to find finishing defects in doors and windows, plumbing, painting and so on. The Handover Certificate is where the deadlines for remedying these defects are set as a guarantee of delivery.
f) It must attach the final certificate of works, signed by the works director and the director of the works’ execution.
Although it might seem that the Handover Certificate is a legal requirement only for large works or projects, this is not the case. A simple installation, one-off maintenance work, a refurbishment, and so on, fall within the scope of this document. As we have seen, it officially records the end of the works (with legal effects protected by the aforementioned Law), while also providing the client and contractor with reassurance, security and confidence.
How can Mela help you digitalise, complete, store, share and send the Handover Certificate?
It is clear that managing documentation in paper format has many disadvantages, but nowadays the difficulty of sharing it easily stands out.
Digitalising documentation ensures better safekeeping, reduces the risk of misplacement or loss, and allows you to link the same document to several projects, tasks and works. It saves costs on paper, printing ink, storage and search time. If the Handover Certificate, or any other works-related documentation, is created digitally from the outset, we can always print it on paper if necessary.
Although there is no single Handover Certificate template, as we have seen, Spanish Law 38 /1999, the “Ley de Ordenación de la Edificación” (Building Regulations Act), does establish mandatory requirements that must be included, at a minimum, in every Certificate to guarantee its legal validity. Every project is different, and so is every client.
To make completion and sending easier, adapt to the client’s needs and comply with the required legal requirements, Mela provides you with a template. You can modify it in a very easy and intuitive way, link it to works, a phase of the works or a task, and store it so that you can quickly and easily locate it later. You can also sign it directly in the application, both yourself and the client, and share it with anyone you consider necessary.
Conclusions.
a) The Handover Certificate is a legally required document that guarantees, for both the developer and the client, compliance with the agreements made before the works began regarding deadlines, quality, costs and any claims or non-conformities, together with their remedy deadlines.
b) Mela provides a “standard” digital template containing the essential requirements set out in the Law. This template can be modified / adapted to your own needs or those of the client, and used to create as many digital templates as necessary. All parties can sign them, they can be shared, attached to an entire project or a phase of the works and, where necessary, used as an official document accepting and/or remedying the client’s non-conformities.