Work Progress Report (SAL): a complete guide for contractors, professionals and clients

The Work Progress Report (SAL) is one of the most important tools in construction site management. It makes it possible to monitor the actual execution of works, certify completed works and authorise the related payments. Whether for public contracts, private works or renovation projects, the SAL is a fundamental document for ensuring transparency, financial control and proper activity planning. In this in-depth guide, we will look at what the SAL is, how it works, who prepares it, what information it must contain, how it is calculated and what differences exist between public and private works. We will also examine the most common mistakes and best practices for efficiently managing construction progress.

SAL: complete guide

This guide describes the SAL in the Italian context. The rules for public contracts and the arrangements agreed for private works must be kept distinct.

What is a Work Progress Report (SAL)

The Stato Avanzamento Lavori, commonly referred to by the acronym SAL, is the technical and accounting document certifying the actual execution of works carried out on a construction site at a given time.

In practical terms, the SAL captures the actual state of the work and makes it possible to quantify financially the works already completed. Through this document, it is possible to check which activities have been completed, which still have to be carried out and the financial value of the completed works.

The concept of the SAL is closely connected with construction site accounts. Each stage of progress is compared with the bill of quantities and the contract agreed between the client and the contractor.

The main aim is to avoid disputes and ensure that payments are made solely on the basis of works that have actually been completed and can be verified.

For modern, structured management of construction site operations, many contractors use dedicated software such as the solutions available on Mela Work, which enable progress, operational activities and technical documentation to be monitored in real time.

What is the SAL used for on construction sites

The SAL plays an essential role from several perspectives: technical, financial, administrative and contractual.

From a financial perspective, it makes it possible to determine the amounts to be paid to the executing contractor. Without a validated Work Progress Report, payment for the works could be arbitrary or inadequately justified.

From a management perspective, the SAL enables progress on the site to be monitored and the actual situation to be compared with the planned one.

The main benefits are:

  • ongoing cost control;
  • monitoring of work progress;
  • verification of completion timescales;
  • fewer disputes between the parties;
  • greater transparency in the project's financial management;
  • support for administrative reporting.

In complex projects involving numerous work packages and several contractors, the SAL is an indispensable tool for maintaining operational and financial control of the project.

Who prepares the SAL

The SAL is generally prepared by the Works Director.

This professional is responsible for verifying that the works have actually been completed, checking the quantities completed and comparing them with the project and contractual documents.

The Works Director carries this out through:

  1. site inspections;
  2. checks on completed works;
  3. measurement and accounting;
  4. updating the technical documentation;
  5. issuing the SAL.

In the public sector, these activities are governed by the new Italian Public Contracts Code (Codice dei Contratti Pubblici; D.Lgs. 36/2023) and the related implementing provisions published by the Ministry of Infrastructure and Transport.

In the private sector, by contrast, the arrangements may be defined contractually by the parties, while retaining similar principles of verification and certification.

How the work progress process works

Managing a Work Progress Report normally follows a well-defined process.

It begins by recording the works that have actually been completed. The Works Director compares what has been carried out with the bill of quantities and the project timetable.

The works are then measured and entered into the accounts.

Once the quantities have been verified, their financial value is assigned on the basis of the prices established in the contract.

The process concludes with:

  • preparation of the SAL;
  • technical validation;
  • issue of the payment certificate;
  • settlement of the sums due.

The entire workflow can be considerably simplified with digital tools that collect data directly from the site and centralise operational documentation. Solutions such as those offered by Mela Work can improve communication between the office and the site and reduce the risk of administrative errors.

What a SAL contains

A Work Progress Report must include precise, verifiable information.

It generally includes:

Identifying details of the project

  • project name;
  • client;
  • executing contractor;
  • construction site location;
  • contractual references.

Technical data

  • completed works;
  • quantities completed;
  • completion percentages;
  • any variations.

Financial data

  • amounts accrued;
  • amounts already paid;
  • outstanding amounts;
  • contractual retentions.

Attached documentation

  • measurement books;
  • accounting records;
  • photographic documentation;
  • inspection reports.

Complete information is essential to ensure the document's validity and facilitate any subsequent checks.

How to calculate a Work Progress Report

The SAL is calculated starting from the quantities actually completed.

For each bill-of-quantities item, the completed quantities are recorded and multiplied by the unit price specified in the contract.

For example:

  • masonry completed: 100 m²;
  • unit price: 50 €/m²;
  • accrued value: 5.000 €.

The same procedure is applied to all works entered into the accounts.

The sum of the values determines the total amount of the SAL.

Where there are variations, reservations or additional works, these are entered into the accounts according to the arrangements provided for by the legislation or contractual agreements.

It is important to stress that the SAL is not simply a theoretical completion percentage, but a certification based on actual, documented measurements.

SALs for public works

In the public sector, the SAL is even more significant because it is closely linked to public procurement rules.

The preparation and approval procedures must comply with the provisions of the Public Contracts Code and the guidelines issued by the competent authorities.

In this context, the SAL is used to:

  • certify contract progress;
  • authorise payments;
  • verify compliance with the project timetable;
  • monitor the use of public resources.

The documentation must be particularly accurate because it may be subject to checks by inspection bodies, contracting authorities and supervisory organisations.

Further information can be found on the official ANAC website

SALs for private works

The SAL is also a fundamental tool on private construction sites.

Contracts very often provide for staged payments linked to the achievement of specific progress stages.

A typical example concerns the construction of a new home:

  • completion of the foundations;
  • construction of the structure;
  • completion of the roof;
  • internal finishes;
  • final handover.

When each stage is reached, the relevant SAL is issued and payment is authorised.

This arrangement benefits both the client and the contractor, as it reduces financial risk and provides greater transparency in managing the project.

Payment certificate and SAL

The SAL and the payment certificate are often confused, but they are separate documents.

The SAL documents and quantifies the completed works. In Italian public contracts, the Works Director sends the SAL to the RUP, who issues the payment certificate under Annex II.14, art. 12, paragraph 1, letter d), of D.Lgs. 36/2023.

The certificate is the separate step preceding settlement by the contracting authority; it is not the same as the SAL. Private works follow the arrangements set out in the contract.

In other words, the SAL provides the technical basis for issuing the financial certificate.

Proper management of these documents is essential to avoid payment delays and potential contractual disputes.

Mistakes to avoid when managing the SAL

Managing work progress can present several challenges.

The most common mistakes include:

  • incomplete recording of works;
  • insufficient documentation;
  • untimely updates;
  • failure to verify quantities;
  • accounting errors;
  • poor communication between the technical office and the site.

To avoid these issues, it is essential to adopt standardised procedures and use digital tools that allow data to be collected directly in the field.

Integrating operational activities, photographic documentation and works management makes it possible to produce more accurate and easily verifiable SALs.

Digitalisation and digital management of work progress

Digital transformation is profoundly changing how construction sites are managed.

Today, many contractors are moving away from Excel spreadsheets, paper documents and fragmented communications in favour of integrated operational management platforms.

Using specialised software, it is possible to:

  • record activities in real time;
  • capture geolocated photographs;
  • monitor work progress;
  • archive technical documents;
  • share information between the office and the site;
  • generate up-to-date reports.

Using digital tools such as Mela Work improves activity traceability and supports the correct preparation of the documentation needed to account for and monitor work progress.

Immediate access to information also enables faster, data-based decisions, improving the project's overall efficiency.

Conclusions

The Work Progress Report is one of the most important tools in the financial and technical management of any construction site.

The SAL makes it possible to certify completed works, control costs, authorise payments and ensure transparency among all parties involved in the project.

Whether for public contracts or private works, properly managing progress helps reduce risks, improve operational control and increase the construction site's overall efficiency.

Adopting digital processes and specialised platforms is an increasingly important competitive advantage for contractors, Works Directors and clients who want to manage projects in a modern, structured way and in line with the sector's best practices.

FAQ

What is a SAL in construction?

The SAL (Stato Avanzamento Lavori) is the document that certifies the works actually completed at a given point on the construction site and quantifies their financial value.

Who signs the Work Progress Report?

The SAL is generally prepared and validated by the Works Director, who verifies that the works have been correctly completed and accounted for.

How often is a SAL issued?

The frequency depends on the contract and the type of project. It may be monthly, quarterly or linked to the achievement of specific progress stages.

What is the difference between a SAL and a payment certificate?

The SAL certifies the completed works, while the payment certificate authorises the financial settlement of the amounts accrued on the basis of the SAL itself.