How to complete a site diary: 4 points not to forget
Learn what to record in an Italian site diary, from daily activities and weather to instructions, changes, incidents and digital record-keeping.
A short guide to completing a site diary with ease—and if it is as simple as a chat, even better! Let’s see why.
How to complete a site diary
How do you complete a site diary? A site diary is the legally required document for Italian construction sites, which makes it possible to monitor a site’s technical and financial progress day by day. Everything that happens on site each day must be recorded in the site diary.
How to complete a site diary. What should you record in the site diary?
But how can you proceed correctly and in compliance with the law? Here are the things to record, according to Decree of the Italian Ministry of Infrastructure no. 49 (Italian: Decreto del Ministero delle Infrastrutture) dated 7/03/2018.
1. SITE ACTIVITIES AND HOW THEY ARE CARRIED OUT
In the site diary, you must record the order and method in which the work is carried out, the number and qualifications of the workers, the technical equipment and anything else that may be useful for recording the daily progress of work on site.
2. WEATHER, GROUND CONDITIONS AND, WHERE RELEVANT, WATER CONDITIONS
You must also record everything that happens and could affect the progress of work on site, including weather observations, any hydrometric data and information about the nature of the ground.
3. ORDERS, INSTRUCTIONS, MINUTES AND ANY CHANGES
You must also record everything relating to the technical and financial progress of the work in the diary: the list of supplies provided by the contractor, documented by the relevant paid invoices; service orders, instructions and requirements issued by the RUP and the works director (if that is not you); reports addressed to the person responsible for the procedure; and minutes recording established facts or the carrying out of tests.
4. SUSPENSIONS AND RESUMPTIONS OF WORK, BUDGET CHANGES AND ACCIDENTS
You must also record any disputes, suspensions and resumptions of work, and any variations or price changes. You should also note whether any event caused an accident at work.
Click here for more information
Who checks the site diary?
The works director will do this. Approximately every ten days, and in any event during each visit, they will check the accuracy of what has been written in the site diary and add any observations, requirements and warnings they consider appropriate, together with the date and their signature.
How do you complete a site diary: by hand or digitally?
DM (Italian: Decreto del Ministero delle Infrastrutture) 49/2018 Article 15 establishes that work accounts must be kept using “specific electronic tools” that use “also online” platforms. This is because digital tools allow you to track work correctly and have the exact date on which it was carried out.
If you have always been used to completing site diaries by hand, don’t be discouraged: we have a very simple solution designed specifically for you. Your work keeps you busy for many hours, you are already very good at doing it, and you certainly do not need to be an IT specialist to carry it out even more efficiently and effectively.
With Mela, your ideal solution is in your pocket: to write down what happens on site each day, you have a chat very similar to the one you normally use to chat with friends or colleagues from your smartphone, and with one click you can download your site diary.
What benefits does an automated site diary offer?
For you, moving from paper to digital means a range of benefits. With an intuitive, easy-to-use application such as Mela, you can avoid having to learn complicated management software and keep track of your site at all times, even remotely.
Work faster! Save time and energy
You will no longer have to spend evenings or nights completing handwritten reports, checking where and when the workmanship error your client disputed occurred, working out who did what and why the site is behind schedule…Everything is recorded on Mela, and data from your mobile is immediately sent to your computer.
Reduce workmanship errors, frustration and headaches
With Mela, you can monitor what is happening on site in real time and immediately find out whether there have been errors or inaccuracies in the work. You therefore save on reworking costs, while also avoiding errors caused by misunderstandings and dissatisfied clients. The result: higher profits for you!
Control the site while avoiding delays and costly variations
With Mela, you avoid fragmented communication and significantly reduce the risk of disputes or payment delays, because your site is in the palm of your hand and you can keep an eye on everything in one app, even when you are not physically there.
Travel light, avoiding loose sheets and illegible handwriting
With Mela, you can say goodbye to sheets of paper scattered who knows where, and to carrying laptops or other bulky items around the site, because you communicate everything via chat.