BUILDING PERMIT: what it is, costs, timescales and practical examples
A practical guide to the Italian building permit: when it is required, who can apply, costs, timescales, sanctions and the main steps.
The building permit (PDC) is an application regulated by Art.10 of the Consolidated Building Act (Italian: Testo Unico dell’Edilizia; DPR 380/01). In this article, we will look at what it involves in detail and provide a comprehensive guide covering the most frequently asked questions, with practical examples concerning this planning permission.
Everything you need to know about building permits
Contents:
Introduction:
What is a building permit?
A building permit is a fundamental planning permission granted by the relevant local council for various types of building work. It is governed by national, regional and local regulations. The application for a permit depends on several factors, including the type of work, the geographical area and the presence of landscape restrictions.
When is a building permit required?
Under Art. 10 of the Consolidated Building Act (Italian: Testo Unico dell’Edilizia), the works requiring a building permit are:
a) new construction work;
b) urban redevelopment work;
c) building renovation work that results in a building which is wholly or partly different from the previous one, where it also involves changes to the overall volume of buildings or, solely for properties located in homogeneous zone A, changes of use. This also includes work involving changes to the outline or overall volume of buildings, or to the elevations of properties protected under the Code of Cultural Heritage and Landscape under Legislative Decree 22 January 2004, no. 42, as well as building renovation work involving the demolition and reconstruction of buildings located in areas protected under Articles 136, paragraph 1, letters c) and d), and 142 of the code under Legislative Decree 22 January 2004, no. 42, or the restoration of collapsed or demolished buildings located in the same areas. In both cases, this applies where changes are planned to the outline, elevations, footprint, plan-volumetric and typological features of the previous building, or where increases in volume are planned.
It is important to remember, however, that the regions play a fundamental role in the decision-making process, since, as stated in DPR 380/01, at Art.10, Chapter 2,:
2. The regions establish by law which changes, connected or unconnected to physical transformations, in the use of properties or parts thereof are subject to a building permit or a certified notification of commencement of works (SCIA).
3. The regions may also identify by law additional works which, in relation to their impact on the territory and on the urban planning load, are subject to the prior issue of a building permit.
Who can submit the application?
The building permit may be requested by the property owner or by authorised professionals, such as architects, engineers or surveyors.
Who issues the building permit?
Competent authorities and local regulations
The process of obtaining a building permit is closely linked to local authorities and the regulations in force. Identifying the body responsible for issuing the permit is the essential first step.
Local authorities
Generally, the council’s one-stop building office (SUE) in the municipality where the building work is located is the competent authority for issuing the building permit. However, the organisation of responsibilities may differ in some regions.
→ Have you checked whether your project falls under the council’s remit, or whether your region has additional provisions concerning the competent authorities?
→ Have you involved a professional to facilitate the building permit application process and ensure that the documentation is correct?
It is good practice to entrust the submission of a building permit application to industry professionals, such as architects, engineers or surveyors. These professionals play a key role in ensuring that the submitted documentation complies with local and national regulations.
Practical example:
Imagine that you want to build a new home in zone A, an area with historic and artistic characteristics. In this case, the council becomes the main point of contact for obtaining the building permit. By involving a qualified professional, you can simplify the process and ensure that your project complies with regional and local regulations so that it can be approved.
How to apply for a building permit
The procedure for applying for a PDC is a crucial step, and understanding all the stages is necessary to ensure a smooth process.
The main steps involved in applying for a building permit are as follows:
Preliminary design: start by preparing a preliminary design that describes the building work you intend to carry out in detail. This should include plans, technical drawings and descriptive reports.
Appointed professional: involve a qualified professional, such as an architect or surveyor, to prepare the design in accordance with local and national regulations. The professional will be responsible for attaching all the required technical documents and documentation specified by the building regulations.
Submission of the documentation: submit the documentation to the competent council. This step is crucial and must be completed accurately to avoid delays or refusals.
→ Have you prepared an accurate preliminary design for your building work?
→ Have you appointed a qualified professional to ensure that the design is submitted correctly?
Practical example:
Suppose you are planning to extend your home. After preparing a detailed preliminary design, you contact a surveyor to formally prepare the required documents. The professional checks that the design complies with local and national regulations. The complete documentation is submitted to the council, ensuring a smooth procedure. Involving a specialised professional simplifies the process and avoids bureaucratic complications.
Building permit costs, timescales and deadlines
**→ What are the costs of a building permit?
**
A building permit involves paying a contribution linked to urbanisation charges and construction costs. The urbanisation charges are paid to the council or may be replaced by the direct construction of works. The charges are set by the council in accordance with regional tables.
The contribution towards construction costs, determined when the permit is issued, is paid during the work.
Construction costs for new buildings are set at regional level, with a percentage included in the permit contribution. For work on existing buildings, the cost is related to the work involved, with possible reductions for heritage recovery.
Reductions or exemptions apply in specific cases, such as subsidised housing, work on State-owned properties, renovations, public works and projects using renewable sources. Reductions of up to 20% may be available for urban regeneration, energy efficiency and seismic safety work, at the councils’ discretion.
→ How long does the process of obtaining a building permit take?
The process of obtaining a building permit follows a series of key stages, with timescales defined by the legislation in force. Within 60 days of the application being submitted, the officer responsible for the procedure at the relevant council issues a “Proposed decision”. During this period, additions or amendments to the design may be requested, extending the process.
Within 30 days of issuing the proposed decision, the officer issues the final decision, notifying the applicant and publishing it on the council’s official noticeboard.
→ How can environmental restrictions affect the time taken to issue a building permit, and what does a consent decision mean in this context?
If the property is subject to environmental, landscape or cultural restrictions, the 30-day period begins when the consent decision is issued. This approach aims to ensure an accurate assessment of particularly sensitive situations.
→ What deadlines must be met, what factors might require an extension to the building permit, and how can one be obtained?
The building permit sets the deadlines for starting and completing the work. The start date may not be more than one year after issue, while completion must take place within 3 years of the work starting. A one-year extension is possible for specific reasons, such as unforeseen factors or complex technical characteristics.
→ What are the benefits of using a digital approach to manage building permit timescales?
Under _Art. 20 of the Consolidated Building Act (Italian: Testo Unico dell’Edilizia; DPR 380/01), the one-stop building office (SUE) issues, electronically and within 15 days of the request, a statement of the procedural timescales. This applies where no additional documentation has been requested and no refusal decisions have been issued.
Breaches, penalties and unlawful building work: what to know about building permits
→ What legal and financial consequences may arise for anyone carrying out building work requiring a permit without the relevant planning permission?
The relevant council office has the power to order the demolition or removal of works carried out in total breach of the building permit or without one. If the order is not complied with, it may confiscate the building. The law provides for criminal proceedings in the event of failure to comply with the order, with significant fines.
If building work carried out without planning permission is not removed within the prescribed period, the council may intervene directly, at the expense of the person responsible for the breach.
→ How can breaches involving building work carried out without planning permission be managed?
Let us take an example. Imagine that we are involved in a renovation project and, due to a failure to pay attention to local regulations, discover that some work was carried out without a building permit. In this case, the various options must be assessed. Applying for a retrospective building permit could be a strategic solution, if accepted by the authority responsible for the assessment.
However, to avoid measures of varying severity, it is always better to act promptly to avoid more serious penalties and preserve the integrity of the project.
We have nearly reached the end of this guide to building permits. To provide a better overall understanding, we will conclude with a practical example involving the construction of a new home, summarising all the concepts covered so far.
Practical example: building a new home
Starting the project: applying for a building permit
Imagine that we want to build our home on a recently purchased plot of land. The first stage involves applying for a building permit.
→ What essential documents must be submitted with the PDC application?
As owners, we must submit the necessary documentation to the council, including the designs required by the local building regulations and a declaration that the work complies with the regulations in force.
Approval and starting work: granting the permit
→ What is the typical timescale for obtaining approval and being granted a building permit?
After submitting the application, we must wait for approval. The officer responsible for the procedure issues a proposed decision within 60 days of the submission date. Once approval has been obtained, the building permit is issued and notified.
Construction: stages and deadlines
→ What factors might require an extension to the completion deadlines?
With the permit in hand, we can begin the work. The building permit specifies the deadlines for starting and completing the work. We must meet the start deadline, which may not be more than one year after issue, and the completion deadline, which is within three years of the work starting.
Digital monitoring and registration: the one-stop building office
→ How does the one-stop office simplify the monitoring and administrative management of the work?
During construction, applications and communications are managed through the one-stop building office. Electronically recording work progress is essential, and compliance certificates may be issued within 15 days of the request.
Completing the work and the home: the end of the process
→ What are the final administrative and inspection steps before the new home can be occupied?
Once the work is complete, the officer responsible for the procedure issues the final decision within 30 days of the initial proposal. The document is published on the official noticeboard, confirming that the work complies with the requirements. The home is now ready to be occupied.
This example shows how the process, starting with the building permit application, guides you through all the stages required to build a new home. Correctly managing each step is essential to ensure compliance with regulations, avoid penalties and fully enjoy the new living space.
Conclusions
How to simplify work progress management by digitising construction sites
In conclusion, obtaining a building permit and completing the construction of a home is a complex, multi-stage process requiring attention to detail, compliance with the regulations in force and efficient time management.
The keys to an efficient process: digitising construction sites
To simplify and optimise this process, you can rely on a construction-site digitisation app. This advanced solution enables you to manage every stage of your construction project efficiently and collaboratively.
How it works: optimise your construction-site management
Integrated chat: communicate directly with the entire project team through a dedicated chat, enabling greater speed and transparency.
Photo monitoring: easily upload site photos, documenting every stage of construction and creating a detailed visual archive
Digital signature: simplify the management of official documents by signing digitally through the app, removing the need for paper documents.
Remote inspections: carry out remote inspections in real time, allowing the site manager or client to monitor the site without being physically present
If you work in construction and are interested in discovering the many other benefits you could bring to your daily work, I invite you to download the Mela app and try the product for yourself.