Bill of quantities: a valuable tool for site accounting in 2023
Learn what an estimated bill of quantities is, who prepares it and how it supports construction cost planning, site accounting and progress tracking.
What is an estimated bill of quantities, how is it prepared, who prepares it and what does it include? Finally, what is the difference between a bill of quantities and an estimated bill of quantities? Let’s take a look together!
The estimated bill of quantities
What exactly is an estimated bill of quantities? What is it used for, and what is the difference between a standard bill of quantities and an estimated bill of quantities? In the following sections, we answer all these questions and look at an example of an estimated bill of quantities.
Bill of quantities and estimated bill of quantities: definitions
To understand what an estimated bill of quantities is, let’s start with the definition of a bill of quantities. Do you have the classic shopping list in mind? Like this, a bill of quantities is a document that states which materials, people and activities are needed to complete a project.
Starting from this definition of a bill of quantities, an estimated bill of quantities adds the aspect of price: how much do the materials, activities and equipment needed for construction cost?
An estimated bill of quantities is therefore a list in which each item contains at least 3 elements:
1. A description of the item
2. The quantity
3. The price
The estimated bill of quantities must also describe the materials and activities planned for each part of the work, with the correct quantities and unit prices for each item.
The estimated bill of quantities is intended to estimate the cost of carrying out the work involved in constructing a building.
The estimated bill of quantities is used in both public and private works
The estimated bill of quantities is made mandatory by legislation for public works (Italy’s Codice appalti (Public Contracts Code), Legislative Decree 18 April 2016, no. 50) and is increasingly used in private works as a contractual tool for regulating the relationship between the client and the contractor.
As we have seen, prepared on the basis of a project and starting from the bill of quantities, the estimated bill of quantities is used both by those requesting the work – the client – and by those carrying it out – the contracting and executing companies.
The estimated bill of quantities allows the client to plan the investment needed to complete the work using a realistic estimate and request quotes from the construction companies appointed to carry out the work.
On the other hand, based on the estimated bill of quantities, the contractor can submit its offer for carrying out the works included in the detailed design and establish what is needed on site to construct the planned work.
Difference between an estimated bill of quantities and a bill of quantities
It can therefore be said that a bill of quantities and an estimated bill of quantities are two quite different documents: the first establishes the quantities of materials needed for a construction project, while the second contains the financial estimate of those quantities and the forecast total value of the work.
Without a bill of quantities, it is therefore not possible to prepare an estimated bill of quantities, because the latter is created by adding a unit price to the quantities for each activity.
Bill of quantities: a template
A bill of quantities template for each activity being measured will contain these columns: equal parts, indicating the number of identical elements, followed by length, width, height and weight.
For building services design, the bill of quantities template generally includes only the quantity column, into which the result of a single calculation formula is entered, obtained by multiplying: equal parts, length, width, height and weight.
Estimated bill of quantities: an example
An estimated bill of quantities is instead an analytical process for calculating the value of the various activities and the total cost of the work. It is based on multiplying the quantity of each activity by the corresponding unit price in the project price list, thereby obtaining the partial cost of each activity. The sum of all partial costs gives the total project cost.
To prepare the estimated bill of quantities, we can use a template with additional columns for the unit price of each activity and the partial amount (the partial cost of each activity and the total project cost), compared with the standard bill of quantities template.
How the Mela app can help prepare an estimated bill of quantities
Mela supports both the Works Director and the contractor carrying out the work in reporting site production and monitoring progress in relation to the bill of quantities.
The app allows each party involved in the project to record production daily and classify it according to the bill of quantities items. Here’s how:
- Creating a dedicated accounts section for the bill of quantities.
- Adding individual activities without specifying their unit cost. This approach focuses on measurements to make it easier to complete the measurement book and the progress report.
- The site manager reports site production day by day in a dedicated task shared with the Works Director. This is managed using Mela’s Accounts feature.
- Using captions and tags, the site manager indicates the specific location of the work (floor, room, flat, etc.).
- The site manager also records any variations from the bill of quantities and identifies them with specific tags so they are visible and not overlooked.
- With a single click, the site manager and the Works Director obtain the completed and shared progress report.
In this way, Mela simplifies the process of reporting and monitoring work progress against the bill of quantities.
Questions and answers
1. What is an estimated bill of quantities?
An estimated bill of quantities is a document intended to estimate the cost of carrying out the work involved in constructing a building, or part of one.
2. What is the difference between a bill of quantities and an estimated bill of quantities?
The difference between a bill of quantities and an estimated bill of quantities is that the latter also adds an estimate of the cost of completing the work: how much do the materials, activities and equipment needed for construction cost?
3. Is an estimated bill of quantities required by law?
Yes, the legislation (Italy’s Codice appalti (Public Contracts Code), Legislative Decree 18 April 2016, no. 50) establishes that a bill of quantities is mandatory for public works. However, this document is also widely used in the private sector because of its usefulness as a contractual document between the client and the contractor carrying out the work.
4. Who uses an estimated bill of quantities in the private sector?
An estimated bill of quantities is used both by the client commissioning the work and by the companies responsible for carrying it out.