Work Progress Statement (SAL) explained clearly: documents and rules under the new 2023 Public Contracts Code
Understand Work Progress Statements: required documents, Italian rules, the roles of the Works Director and RUP, and how to digitise the process.
A clear explanation of what a Work Progress Statement means: which documents are required, the rules under the new Public Contracts Code of 2023, the role of the Works Director and that of the RUP. Finally, how to digitise the process and the preparation of the SAL.
Work Progress Statement
Why prepare a SAL – Work Progress Statement?
In construction, the SAL is the document that establishes the possibility of paying for part of the work carried out.
On a construction site, both the client (customer or contracting authority, however you wish to call it) and the contractor (the company carrying out the work) may be interested in paying for part of the work before it is finished. This is referred to as an advance or payment based on a Work Progress Statement. Once the work is complete, the payment for the entire project is completed.
For example: if a council awards the construction of a new school to a contractor, the project will probably cost several million euros and could last several years. If the contractor had to wait until all the work was finished before starting to invoice and receive payment, it would have to find other ways to finance itself during the work, taking on financing costs that it would consequently have to pass on to the client. It is therefore in both parties’ interests to allow the contractor to invoice advance payments (advances against the agreed amount for the completion of the entire project) as the work progresses: these advances are approved through the SAL.
Each contract between client and contractor determines the scheme these advances must follow, and normally there are 2 broad approaches:
- Time-based SALs – at the end of each month, the progress of the work is checked and the advance due is paid
- Milestone SALs – the SAL does not follow time deadlines but the achievement of specific stages in the project (at the start of the site, the roof, completed installations, etc…)
This logical and contractual process applies to any type of contract but, for public contracts, it is not only mandatory but also regulated by the Public Contracts Code.
Note on the new Public Contracts Code (Codice dei contratti pubblici) 2023:
Here you can download a copy of the new Public Contracts Code issued in March 2023 and in force from 1 July 2023.
New Public Contracts Code 2023 – Official Gazette
Main characteristics of the SAL
- The SAL is the document that unlocks payment for the work
- At least 2 parties are involved in this document
- The Works Director (representing the paying client)
- The company carrying out the work (sometimes the consortium or group of companies)
- The following steps must be followed to prepare a SAL:
- Complete the measurement book
- Turn the measurement book into the accounting register
- Issue the SAL
There are different types of SAL: measured, lump-sum and force-account
There is a formal distinction in how payment for the work can be managed and therefore how SALs can be issued
- measured
- lump-sum
- force-account
A SAL is also prepared when the work is quantified (and paid) on a “lump-sum” basis rather than by measurement: in these cases, the contract establishes payment deadlines according to some criterion (time, amount, etc., always with reference to a percentage of work progress). For “in economia” (force-account) work, by definition there is no concept of a SAL because it is settled on a actual-cost (time-and-materials) basis, meaning the total labour hours completed are recorded (payment is based on the “quantity of work” carried out, regardless of the progress of the project).
It can be seen that these different types of SAL correspond to the definitions given at the beginning of the article for time-based and milestone SALs.
The role of the Works Director
For public contracts in particular, but generally for any contract, the Works Director is the person responsible for managing the entire process that leads to the issue of the SAL.
In fact, the Works Director has two primary responsibilities towards the client:
- Check (and promote – assist with) and certify the progress of the work
- Check and certify the quality of the completed works (against the design)
In particular, the Public Contracts Code (in Annex 2-14 on the management of works and management of contract performance. How activities in the performance phase are carried out. Testing and verification of compliance.) establishes that, once the Works Director has measured the works actually completed on site and prepared the measurement book and accounting register, they may prepare the Work Progress Statement and submit it to the RUP for the issue of the payment certificate. At this point, the supplier can invoice.
The Works Director’s main tool for tracking all their work is the Works Journal, the diary describing the life of the site and the construction of the project: like a ship’s logbook for a vessel at sea.
To find out more about the works journal, read: Examples of Works Journals
To find out more about the Works Director’s activities and how they can be supported by simple, affordable digital tools, also read: The digital Works Director
An interesting point about the SAL – what is the first reference to the Works Management process in Italian law?
The concept of a Work Progress Statement, understood as a document tracking the execution of a project or part of it and the resulting payment for that work according to the agreements between a public client and private contractor, is as old as state accounting. A large part of the state budget has always been spent on works, after all, bringing with it the need for agreements, checks and payment: we can imagine the Works Director of the pyramids or the Colosseum, and their reasoning around the concept of the SAL would not have been very different (they would certainly have called it something else).
In Italian case law, we found the first reference to oversight of work progress in Article 118 of R.D. 23.05.1924, no. 827, which states verbatim:
“The special regulations for each service shall establish the precautions for assistance, supervision and management necessary to ensure the proper execution of supplies, transport or works, according to their different nature.
When works, transport and supplies are delayed, the persons responsible for supervising their execution must report this to the competent authority for the proper fulfilment of the contract and the application of the penalties provided for therein.”
This article shows both the person who monitors the execution of the work over time, the Works Director, and the end client (the competent authority), whom today we would identify as the Responsabile Unico del Procedimento (RUP, Sole Project Manager).
How to prepare a Work Progress Statement under Italian regulations
The Works Director – while carrying out checks – must measure and record work progress. For this reason, the regulations introduced an accounting document called the Measurement Book, in which the completed works and their measurements are recorded in an orderly manner. These measurements must be taken over time and must show a clear chronological development of the work.
The Measurement Book
Note 1 – The measurement book must be managed jointly by the parties
The Works Director must obtain the contractor’s signature confirming the measurements taken (the revision of the 2023 Code states that the book must be signed immediately by the contractor or the technician representing the contractor). In short, the client (the RUP) wants transparency and shared responsibility between the Works Director and Contractor regarding the measurement of work progress: accurately measuring what has been completed is a fixed and extremely important point for avoiding problems. In this context, the “daily report” plays a fundamental role: read our in-depth article on the subject.
Note 2 – Measurements must be taken against the contract items
This shows us the close relationship between measuring the work actually completed and paying for that work. To pay for the work, I must use the terms of the contract (the items included in it and given an economic value during the award stages), and therefore I must be able to clearly understand from the measurement book which works have actually been completed and then proceed with payment.
It is clear that some works are easy to measure (e.g. how many square metres of asphalt were laid at kilometre 400 of motorway A1 on a given day), while others are more difficult to quantify as physical measurements (e.g. implementing the control logic for the Bologna railway junction). In these cases, things become somewhat more complicated and percentages of the complete project start to be used, but the final concept remains unchanged: the Works Director must monitor work progress, must know it, and must be able to demonstrate it.
Note 3 – Which digital tools to use
Let’s be clear, most measurement books are managed with Excel. This is because it is a very powerful tool. The price to pay is that it represents only part of the process: the calculations, but not traceability. So when the Measurement Book is managed with Excel, it must then be printed, jointly signed and archived (regardless of whether it is maintained by the contractor or the Works Director).
The second option is historical construction accounting software (the Latin ones, the cloud-based ones, etc.). They do everything and cost a lot. They do so much that most Works Directors we know who use this software spend more time “skipping” than entering data. What does that mean? They are too complex. In addition, they were created and designed in the era of the office computer and do not adapt well to the modern needs of increasingly powerful phones and site-based work.
Mela is working to revolutionise this discipline, and the first results are already visible. Try keeping the Measurement Book with Mela’s accounting feature and you will see: enter measurements directly on site, sign them jointly straight away from your mobile phone and it is done. The end.
To find out more, download the app and start trying it out: DOWNLOAD MELA
The Accounting Register
At this point, once the work carried out has been recorded and measured, it is time to assign it an economic value: this operation allows us to create the Accounting Register.
The new Public Contracts Code states: “The accounting register is the document that summarises and centralises the entire accounting of the project, since the corresponding contractual prices are applied to each quantity of work completed and recorded in the book, so as to determine work progress not only in terms of quantities completed but also in terms of the payment accrued by the contractor.”
The SAL – Work Progress Statement
The Work Progress Statement (SAL) is a document that summarises, at a given point in time (there may be several SALs during execution), all the works and supplies carried out from the start of the contract up to that point.
According to the Code, “This document, drawn up from the accounting register, is issued within the terms and according to the procedures indicated in the tender documentation and the contract, for the purpose of paying an advance instalment; for this purpose, the document must specify the payment accrued, the advances already paid and, consequently, the amount of the advance to be paid, based on the difference between the first two items.”
Note on the digital SAL:
Have you discovered how to prepare reports with Mela? And how to manage your SALs effectively? Always remember that the SAL is essentially a report. These two videos may interest you:
Reports notarised via Blockchain
When is the SAL issued?
The key point in the legal definition of a SAL is: “within the terms and according to the procedures indicated in the tender documentation”. Let’s see why.
The SAL is issued according to the terms defined in the contract. Let’s look at a couple of examples.
In one case, the contract says that the SAL is issued at the end of each month. In this case, at the end of the month the Works Director transcribes into the SAL everything contained in the accounting register and authorises payment (or, as we will see below, in the case of public contracts, sends their authorisation to the RUP; but this is a bureaucratic detail). In this example, payments follow the work continuously.
In the second example, the project SALs are to be issued at specific milestones (stages) of the project. In the case of the school, let us assume that the contract provides for the following SALs:
- First SAL – Completion of the roof and all perimeter walls
- Second SAL – Completion of the installations
- Third SAL – Completion of the works
In this case, the Works Director records progress in the measurement book and accounting register, but issues the SAL to initiate payment of the first advance only once the roof and all perimeter walls are complete. During the construction of the project, there may be times when the accounting register contains a certain financial value of completed works that has not yet entered the payment process.
Issue of the payment certificate by the RUP
As stated directly in the Code: “The Works Director immediately sends the Work Progress Statement to the RUP, who issues the payment certificate; the RUP, after checking the contractor’s social security compliance, sends the payment certificate to the contracting authority for the issue of the payment order; each payment certificate issued by the RUP is recorded in the accounting register.”
The process can be summarised as follows:
- The Works Director issues the SAL
- The Works Director submits the SAL to the RUP
- The RUP checks the contractor’s social security compliance (DURC not expired)
- The RUP issues the payment certificate (within 7 days of receiving the SAL)
- The RUP delivers the payment certificate to the treasury
- Issue of the payment order in favour of the contractor (within 30 days of receiving the payment certificate).
- The contractor may issue an invoice
Yes, this process speaks bureaucratic language, but that is how it is.
What is the SIL and how does it differ from the SAL?
In the procedures of many large construction companies, as well as those of structured and public clients, references are often found to a mysterious SIL (Internal Work Status), with statements such as: “The site manager must prepare and sign, during construction and at defined intervals, an Internal Work Status (SIL) corresponding to the actual production for the client, regardless of the accounting of the official SALs.”
It is important to note that the Public Contracts Code does not provide for any accounting document called a SIL, and its use as we have often seen it, together with the definitions we have encountered, has always brought the Accounting Register to mind. This is indeed an accounting document defined in the Public Contracts Code.
One question remains… who invented this SIL and gave it this name? We believe this habit comes from some slightly outdated construction management software which, starting from a process used by a particular company, exported the concept without correcting the wording as would have been advisable. In general, our advice is to rename this document as an accounting register, especially since in new contracts, for example those under the PNRR, control bodies are increasingly asking for a record of the work actually completed to be shared and countersigned by the Works Director and Contractor. In short, the party paying wants there to be a single document identifying actual work progress, and it can only consist of the Measurement Book and Accounting Register.