How to fill in a site report

Are you required to fill in a site report every day, and does the very thought give you a headache? How can you turn this incredibly boring task, as unwelcome as sand in your sandwich, into a quick, smooth and accurate process?

How to fill in a site report

Site report: what it is and what it is used for

A construction site or work report is a document normally prepared daily when working hours and activities need to be recorded for a client. This document records, day by day, the activities carried out and the materials used.

The document must be signed for acceptance by the end client and therefore also has legal value in the event of disputes or litigation.

The report has another important purpose: to document the decisions made and the approaches taken and, where necessary, to allow them to be changed immediately if more effective solutions are chosen.

The usual process involves completing a paper report in the format chosen by each company. The completed report is then delivered to the office and organised by contract. The information collected is copied into the template (usually Excel, or more rarely management software) used to manage site accounts.

The report is usually accompanied by paper documents produced on site, such as delivery notes, minutes, forms, etc., to supplement the project file kept by the company’s technical office.

THE REPORT IS A KEY DOCUMENT FOR TWO REASONS:

1. To manage site accounts correctly

2. To track each employee’s working hours: the record will be used to prepare their payslip

How do you fill in a site report? 10 things not to miss

A work report generally contains the following information:

  1. The number of the work report, in sequential order
  2. The date on which the work was carried out
  3. Weather notes
  4. The client’s name and details, including, where applicable, the list of subcontracting companies
  5. The location where the work is carried out
  6. A description of the work carried out
  7. The hours worked by each individual worker
  8. The materials used to carry out the work
  9. Any vehicles used
  10. The signature confirming that the work was carried out

Work reports: how many are there, and what types are they?

In addition to the site report, there are two other types of work report:

  1. The intervention report, commonly used for maintenance work
  2. The contract report, used by companies working under contract

If you would like help designing your site reports and improving cost control, read this dedicated guide: go to the article

Have you ever wondered how much time you lose filling in work reports?

Preparing a work report requires you to sit down at a computer after a tiring day working on site and spend time organising all the data collected during the day.

If you are efficient, half an hour a day is enough, but added up over all the working days, that means at least 10 hours at the computer each month—more than a working day!

Time you could save with Mela!

How to fill in a site report: Mela is the right solution!

With Mela, all you need is a smartphone to track every event that takes place on site and create complete, secure reports that comply with regulations, without having to go to the office after work—all with a few simple clicks!

Here’s how:

STEP ONE -> Create a new activity and invite your employees to join it

STEP TWO -> You can now record (and invite your colleagues to do so as well) everything that happens on site. You can choose whichever method is most convenient: messages, audio and video files, or images.

STEP THREE -> At the end of the day, your site report is ready, containing a history of everything that happened during the day. Save or print it from your computer with a single click.

With Mela, you can also manage information from any device (smartphone, tablet, iPad or PC): data is saved in real time on the platform and can be accessed and used by all your work groups.

What are you waiting for? Create your free profile now and start working with Mela!

Site reports for public contracts

For public contracts, the situation is a little more complicated because the rules are set by the Italian Public Contracts Code (Codice Appalti) and enforced by the Works Director. These rules specify how site accounts must be kept to ensure quality and transparency for the public client. In particular, they state that, before being paid for, works must be measured and entered in the accounts register. Payment will then follow the progress payment certificates (SAL) as defined in the contract.

Are work reports governed by the Public Contracts Code? No. Everyone can prepare their work reports as they wish. But let’s see why work reports are also—and above all—important in public contracts.

The starting point for public-contract accounting is the site log. Historically, the site log was a paper book managed under the responsibility of the Works Director, just as work reports managed under the responsibility of the site manager (and internal to the contractor) were also paper-based. For this reason, they were treated as two separate documents. But are they really so different? Below is a comparison between the entries that the Works Director must record in the site log and the typical entries in a work report.

Table
Site logWork reports
Site/Date/ClientWeather notesDescription of activities carried outList of companies present on siteNumber of workers present on site and their qualificationsTechnical equipment and vehicles used to carry out the worksList of supplies provided by the contractor, documented by the relevant paid invoicesAny note or event affecting the technical and financial progress of the works, including any accidentsNotes from the Works Director and reports to the RUPMinutes recording facts or testsObjections, suspensions and resumptions of worksProperly authorised variations, amendments or additions to pricesSite/Date/ClientWeather notesDescription of work carried outWorkers present, qualifications and hours workedEquipment and vehicles usedMaterials used to carry out the workAny vehicles usedAny note that helps correctly reconstruct the cost of the completed works

It is clear that the first 8 entries are practically identical, except that in one case they concern a single company, while in the other—the site log—it is necessary to consider that several companies may operate on site at the same time and the Works Director must oversee them all.

The further differences are found in the minutes and service orders, which, if properly digitised, fit perfectly into this framework. In this regard, we recommend reading this article on managing site minutes.

The importance of recording completed work in work reports

Work reports normally contain the information needed to prepare a correct site log, including:

  • The resources used (meaning those present) on site

  • Vehicles and equipment

  • Materials

  • Work carried out

This is the information that a Works Director must record in the project’s site log. In this sense, if they could access and systematically check the reports, their work would be complete.

The problem with sharing this document has always been the sharing of information. How transparent do I want to be?

Our advice for this approach is to share the resources used but not the costs they generated (how much the materials or resources cost the contractor). Today, this distinction is possible through digital tools.

Furthermore, with an app such as Mela, the contractor can share the report with the Works Director so that they can see quantities only, not costs.

The app also makes it possible to attach photos to reports, turning the sequence of reports into a complete site log.

This approach has many advantages:

  • Creates a single, consistent picture of the progress of the works, limiting differences in assessments of progress

  • Makes the Works Director a participant in the company’s daily activity and therefore creates trust, transparency and accountability for both parties

  • Reduces the number of times the same data is transcribed, consequently reducing work and errors.

It is worth noting that many experienced site managers we have met were already doing something similar on paper!

The site manager gets site reports signed by the Works Director or their assistants

Some experienced site managers take the trouble to have all site reports signed by the Works Director’s assistants. These reports included both the resources used (people, materials, vehicles, etc.) and the work carried out, indicating each time whether the items were contractual or extras. In reality, they were preparing both a Measurement Book and a Site Log.

This practice ensures that the contractor does not lose any extras under the contract and greatly simplifies discussions about payment.

A point of caution for the Works Director’s office: check carefully what is signed day by day, because the contractor is building robust documentation with which to submit the bill!

This process is greatly simplified by adopting a digital tool, which avoids having to manage paper copies of documents on site.

The site surveyor uses work reports to update a draft digital Measurement Book shared with the Works Director.

In this example, the contractor takes a further step compared with the previous example. Work reports are managed digitally, and the resulting Measurement Book for the completed works is maintained by the contractor’s site surveyor and shared with the Works Director. This gives both parties a consistent, transparent and up-to-date view of the progress of the works, drastically simplifying management of the project’s accounts.

Questions and answers

What is a site report?

A site report, or daily work report, is a document that can be prepared digitally or on paper and completed by a company’s employees. It contains information about the activities carried out for each contract, each worker’s hours, and the materials and vehicles used.

What is a site report used for?

A site report has two main purposes: tracking working hours and managing each employee’s attendance; the record is used to prepare their payslip and to manage site accounts correctly.

**What are the benefits of a digital site report?
**
With a digital site report, you first of all save a great deal of time—with site apps such as Mela, you can complete it directly on your smartphone on site, sign it and share it—and greatly reduce “human” errors, such as those caused by incorrect handwritten transcriptions.