Example of a site diary: how to complete it correctly
Learn how to complete a site diary correctly, move from paper to digital records, and document construction work with clear, traceable information.
Step by step, let’s look at how to complete a site diary correctly, choosing digital records over a paper register.
Example of a site diary
Listen to our podcast “La chiacchiera dell'Umarell”!
Listen to “Let's talk about... il Giornale dei Lavori” on Spreaker.
A site diary is the document in which everything that happens on a construction site is recorded. It is the accounting document used to track the life of the construction site, day by day, from both a technical and financial point of view.
Under the guidelines established by DM 49/2018, the site diary has a fundamental role in construction-site control and must record at least:
The order, method and activity with which the work progresses
The qualifications and number of workers employed
The technical equipment used to carry out the work
The list of supplies provided by the contractor, documented by their respective paid invoices, as well as anything else concerning the technical and financial progress of the work, including any accidents at work
Details of the circumstances and events relating to the work that may affect it, including weather and hydrometric observations, information about the nature of the ground and any other useful details
Service instructions and instructions from the RUP and the works director
Reports addressed to the RUP
The official records of findings concerning facts or the carrying out of tests
Disputes, suspensions and resumptions of the work
Variations formally ordered, and changes or additions to prices
If we think about our construction sites and having to track this amount of information in the traditional way — see the Buffetti site diary — a headache is guaranteed!
There’s no denying it: the regulations represent a disruptive change from the past. What should we do?
Digitalising construction sites could help us deal with this regulatory burden and simplify the related work. In fact, Italian law goes further and, in Article 15, paragraph 1 (“Work accounts are kept using specific electronic tools that use platforms, including online platforms”), provides for the mandatory use of software applications.
These technologies must enable data exchange in order to optimise information flows between the parties involved in the contract (the works director, the health and safety coordinator during the execution phase, the RUP, testing engineers, the contractor, etc.).
In short, it encourages us to put digital tools and collaboration at the centre of the site diary. Ultimately, the regulation seeks to ensure that the client (the RUP) is always kept transparently informed about the work carried out by the site manager under the watchful eye of the works director. In this respect, the legislation promotes information symmetry and relies on digital tools to ensure speed (efficiency) and traceability.
Let’s go back in time and look at how to complete a paper register
You probably have a good idea of how to complete a site diary in a paper register: the format and method are very similar to an accounting document.
And what is inside the site diary? Generally, each page of the diary is made up of several columns that must describe all the fundamental aspects of constructing a building or other structures.
The following must be recorded:
- The date of the work
- Notes or descriptions of how the work is progressing (for example -> “transporting and assembling scaffolding, preparing the site hut, small crane installed”)
- Weather conditions and any noteworthy events (for example -> “clear skies”, “work interrupted due to rain”, “ground subsidence caused by a severe overnight storm”)
- The resources deployed, divided into human resources (e.g. 1 skilled worker, 4 general workers...) and equipment (e.g. 2 lorries; 1 small crane type …)
- Instructions issued, notes, observations and directions from the works director (e.g. “the client requested a site inspection and quotation for renovating the façade of Giovanni Pascoli school”)
- Signatures
Weaknesses
- In a paper site diary, photos and videos cannot be used, so the information remains limited and simplified. This means an essential detail is missing
- For this reason, it is often necessary to manage an independent archive of site photos, increasing the work and management costs
- Written in illegible handwriting and with subsequent corrections: unclear and inefficient communication creates mistakes, wasted time and money, mistrust and customer dissatisfaction
- They no longer comply with Italian law, since an online platform is required to guarantee the authenticity and security of the data. They may be used only pending digitalisation. Article 15 DL DM 49/2018
Example of a correctly completed digital site diary with Mela
The cloud and mobile technology allow us to greatly simplify compliance with regulatory requirements. With these technologies, we can record written notes directly on site, voice notes (then automatically transcribed by Speach To Text technology, which uses artificial intelligence algorithms), together with photos and videos.
This information is automatically stored in secure, redundant repositories and can be shared with the relevant people, whether they are within the company, part of the works management team or the client (the RUP and their collaborators).
With tools such as Mela, all of this happens in a chat-like environment, minimising difficulties for less digitally experienced staff. By now, practically everyone knows how to use WhatsApp
Everything that happens on site can be recorded and shared, without having to go to the site hut or office and write long, tedious reports at the end of the day. Mela also keeps track of when and where information was entered and allows every change to be signed and locked directly within the chat tool. This ensures compliance with the traceability requirements imposed by the legislation.
Here is how you can open a new construction site, update it daily and finally create complete, detailed and legally compliant reports — the site diary.
Who do you want to include in your construction site?
Starting a new construction site? Open a project and an activity in Mela and share it with the relevant people. See how in this video!
Start a new activity (construction site, project, order, etc...)
Done? Now you can immediately enter all the information needed to work effectively and record everything that happens on site: messages, audio and video files, images and signatures.
The site diary is already done. And if you want, you can also export the PDF version.
With cloud technology, you can manage information from any device (smartphone, tablet or PC), because the data is automatically saved on the platform and can be entered, viewed and used remotely.
The information collected is already the site diary for the construction site, or for the desired construction phase. It is robust, accurate and traceable. It guarantees transparency and can be used to avoid or resolve disputes.
What is more, it can be exported with one click and shared further as needed in PDF format.
…. Here is the result!
Strengths
- With Mela, you always have the construction site under control, increase collaboration and customer trust, and can manage everything on your smartphone without going to the office
- Mela’s timestamp (a sequence of characters representing a date or time) records precisely when a particular event occurred and has legal value
- You get the power of photos and videos without having to manage external archives