Measurement book: what it is, what it is for. What Legislative Decree 36/2023 says
Find out what the measurement book is, what it contains, who compiles it and how digital tools support transparent construction accounting.
What is the measurement book for? Is it mandatory? What does it contain? Here is how to proceed in practice, based on the recent Legislative Decree 36 of 31 March 2023.
Measurement book: how to compile it in light of Legislative Decree 36/2023
The measurement book is the accounting document that makes it possible to establish the quantity of work carried out by the appointed contractor by measuring and classifying the works completed progressively.
The task of measuring the work lies with the works supervisor, who records the measurements in the measurement book during each site visit and indicates the quantities completed. The works supervisor is required to record progressively all activities that constitute an item of expenditure for carrying out a project and, in the event of omissions or irregularities, must answer for them personally before the law.
The measurement book must be a document agreed in adversarial proceedings between the Technical Director, the contractor and the contracting authority: what has been done and how much has been done cannot be subjective!
Digital tools such as the Mela construction app Mela - allow 3 parties to work in an environment where they access a single data source and check its accuracy. Reservations, comments and discussions are tracked with complete transparency.
Measurement book: a definition under the legislation
The precise definition of what the measurement book is and what it must contain appears in Article 183 of the Italian Presidential Decree no. 207/2010 (Regulation implementing the Public Contracts Code, Legislative Decree no. 163/2006), which states that the measurement book must specifically record:
a) the type of work or supply, classified according to the contractual designation;
b) the part of the work completed and the location;
c) dimensioned drawings of the work carried out, where applicable; in the case of work that changes the pre-existing state of things, dimensioned profiles and plans depicting the state of things before and after the work must be attached;
d) any other explanatory notes, in order to demonstrate clearly and accurately, in its various parts, the form and method of execution.
Work must be measured at the same time as it is carried out, and it is essential that measurement proceeds together with execution
The measurement book and the works supervisor
According to Legislative Decree 31 March 2023, no. 36 - Annex 14 - (on which you can read an ANCE commentary), it is the works supervisor’s responsibility to control expenditure related to carrying out the work, and they must ensure that all necessary documents are prepared accurately and promptly.
The measurement book, together with other accounting documents such as the progress report and the site log, makes it possible to establish expenditure on carrying out the work. These documents are, in all respects, valid public records before the law.
The works supervisor ensures that the measurement books are updated and signed immediately by the contractor or by the contractor’s technician present during the measurement survey. For work and supplies justified by invoice, the works supervisor checks that they conform to the quotations accepted previously and to the actual state of the work.
The measurement book and lump-sum works
In the case of lump-sum works, the work is recorded in a specific measurement book, as set out in Annex II.14 of Legislative Decree 36/2023. Whenever a progress status is completed for a specific work category, the works supervisor records the percentage completion of that category, based on the percentage shares of the individual items set out in the contract.
The progressive percentage shares of the individual items in the various work categories are derived from assessments carried out independently by the works supervisor, who can check their order of magnitude against the bill of quantities and estimated costs from which the percentages were derived.
Measurement book: important points to bear in mind
- In addition to the quantity of work completed, the measurement book must also include its precise location, so that it is always available for checks.
- The works supervisor is responsible for certifying the work carried out in the measurement book by adding their signature.
- The contractor must also follow the measurements and sign the measurement book.
The contractor must follow the measurements and sign the measurement book.
How to compile the measurement book
The measurement book essentially consists of two parts: a cover / title page, followed by consecutively numbered internal pages.
The title page includes:
- the subject of the contracted work;
- the number of pages making up the document;
- the signature of the Sole Project Officer (RUP).
The internal pages consist of columns indicating:
- the registration number;
- the tariff code;
- the date of measurement;
- the description of the work and supplies;
- the factors, products and figures;
- additional notes.
Measurement book with the Mela construction app
To produce all accounting records correctly, it is essential today to have access to technology that is powerful yet streamlined, allowing you to carry out surveys directly in the field using your mobile phone and guiding you in producing all accounting documents.
With Mela, you can record everything you need for the measurement book using messages, audio and photos.
The measurement book can be shared, commented on and signed by everyone directly in the app.
Once signed, the measurement book is notarised on the blockchain and archived with a certified date and securely in Mela.
Questions and answers
1. What is the measurement book?
The measurement book is an accounting document that makes it possible to verify the quantity of work carried out by the appointed contractor through the measurement and classification of the works completed progressively.
2. Who compiles the measurement book?
The works supervisor is responsible for preparing the measurement book, which must be done at the same time as the work is carried out. They are required to record accurately all activities that constitute an item of expenditure and, in the event of omissions or irregularities, must answer for them personally.
3. Is the measurement book mandatory under the legislation?
Yes, the measurement book is required under the Italian law described here. Article 183 of Presidential Decree no. 207/2010 sets out precisely what the document must contain, while Legislative Decree 2023/36 - Annex 14 - describes in detail the works supervisor’s obligations for compiling the measurement book.