SAL: what it is and how to prepare the Work Progress Report in 2023

SAL: what it is, how it is prepared and what its function is in 2023, according to the regulations. Everything you need to know about the Work Progress Report.

SAL: what it is and how to prepare the Work Progress Report in 2023

The SAL — Work Progress Report — is an accounting document certifying all works and supplies carried out from the start of the contract until it is issued.

A copy of any lists of new prices is attached to the SAL, also setting out the details of the approval obtained. If these lists are already held by the contracting authority, the works director includes the information in the SAL.

What is the purpose of the SAL?

The purpose of the SAL is to facilitate payment for completed works and, as specified in the new Italian Ministerial Decree on works supervision (d.M. 49 of 2018), it is issued by the works director at the times established in the works contract.

The decree on works supervision establishes that it is the works director’s responsibility to control expenditure connected with the execution of the project or works. They must therefore accurately and promptly complete all accounting documents to ascertain and record costs, which will have legal validity.

In light of the above, it is clear that errors, inaccuracies and delays are not acceptable in this task: the Work Progress Report is in fact a legal document that establishes the current status of the project: how far the works have progressed and what the expenditure will be.

The SAL in the public and private sectors

It is therefore the works director’s responsibility to monitor the development of the works and, where necessary, issue instructions for their execution within the established time and budget limits.

  • In the public sector, the works director issues work progress reports within the deadlines established in the contract and tender documentation. This enables the RUP (Responsabile Unico del Procedimento, Italy’s Sole Person Responsible for the Procedure) to issue certificates for advance payments.
  • In the private sector, the works director performs the same function, enabling the individual client or the person responsible for the contract on behalf of the client (for example, in the case of large private companies) to make payments.

The SAL and the principle of timeliness

When discussing SALs, the principle of timeliness is fundamental: delays are not permitted and everything must happen synchronously. The works director must therefore carry out all activities to ascertain facts generating expenditure at the same time as they occur, keeping pace with the execution of the works.

In particular, the works director must:

  1. Monitor the progress of the works and issue timely instructions to ensure that they are completed within the authorised time and budget limits;
  2. At the times established in the contract, take a snapshot of the accounting register and issue the SAL;
  3. Issue work progress reports within the time limits established in the contract and tender documentation, so that the Responsabile Unico del Procedimento (RUP, Italy’s Sole Person Responsible for the Procedure) can issue certificates for advance payments.

In essence, the works director must determine how much has been completed so far compared with the bill of quantities.

The Site Diary is the main tool used by the works director to record every detail of the site’s progress and the execution of the project. It is a diary that describes the life of the site and the progress of the works in detail, step by step.

The SAL is a public instrument for all legal purposes, intended to record and ascertain facts generating expenditure

The SAL and the regulations: what dm 49 of 2018 establishes

As we have seen, the SAL — Work Progress Report — is a document summarising all works and supplies carried out from the start of the contract up to a specific point in time. In essence, it is a report of the activities completed up to that point during the project. Remember that several SALs may be issued during the execution of a project.

Pursuant to art. 14, paragraph 1, letter d), d.M. 49/2018, the work progress report “drawn up from the accounting register, is issued within the time limits and according to the procedures indicated in the tender documentation and the works contract, for the purpose of paying an advance instalment”.

According to the code, “For this purpose, the document must specify the accrued consideration, the advance payments already made and, consequently, the amount of the advance to be paid, based on the difference between the first two items.”

The SAL and the accounting documents required

The accounting documents that must be considered for the correct preparation of the SAL are

  • The site diary
  • The accounting register
  • The measurement book for the works
  • The payment certificate issued by the RUP
  • The final account for the works

Work progress report (SAL): how it is structured

To maintain a clear picture at all times of the project’s progress and the costs associated with each part of the works, the SAL is made up of several sections, including a cover page and an inner section.

The cover page contains the essential information needed to understand the status of the works, such as

  • The execution time
  • The company’s name
  • The progress of the works
  • Other contractual information

The inner section of the SAL contains a template with columns providing details of each work item:

  • The order number,
  • The identification code
  • A description of the work or work package
  • The quantity completed up to that point
  • The unit price and the total amount accrued in favour of the contractor for each work item

To prepare the SAL effectively, you can rely on the support of a digital tool such as Mela, giving you constant control over all site activities and costs

SAL: how digital tools can simplify the process in 2023

Digital tools, with the streamlined technology of an app like Mela, play an important role on construction sites:

  • They make the collection and preparation of documents, such as photos, videos, messages and documents, faster and more accurate, even remotely.
  • They monitor and manage site accounting in real time: data is sent directly to the accounting register and work progress is continuously updated in real time.
  • For the works director, who often has to manage several sites at the same time, digital tools make it possible to check remotely that the requested works have been completed correctly.

Questions and answers

1. What is the SAL (Work Progress Report)?

The SAL — Work Progress Report — is an accounting document certifying all works and supplies carried out from the start of the contract until it is issued.

2. Who prepares the SAL

The works director is responsible for preparing the SAL: the works director must carry out all activities to ascertain facts generating expenditure at the same time as they occur, keeping pace with the execution of the works.

3. What is the purpose of the SAL?

The purpose of the SAL is to facilitate payment for completed works. As specified in the new decree on works supervision (dm 49 of 2018), it is issued by the works director at the times established in the works contract.