The RUP in the New Public Procurement Code: role, skills and responsibilities
Discover the RUP’s role in Italy’s New Public Procurement Code, including appointment, planning, skills, responsibilities and participation in tender panels.
In March 2023, Italy’s new Public Procurement Code, dgls 36/2023, was published in the Official Gazette. The regulatory framework for public contracts is constantly evolving, and at the centre of this transformation is the figure of the Single Project Manager (RUP), formerly the Single Procedure Manager. This article explores its importance in the context of public contracts, analysing the regulatory changes and the new responsibilities assigned to the RUP.
New Public Procurement Code 2023: the RUP from Single Procedure Manager to Single Project Manager
Contents:
](https://www.mela.work/it/blog/rup-nuovo-codice-appalti-chi-%C3%A8-competenze-responsabilit%C3%A0#link7)**[3.Requirements, skills and duties of the RUP under the New Public Procurement Code 2023](https://www.mela.work/it/blog/rup-nuovo-codice-appalti-chi-%C3%A8-competenze-responsabilit%C3%A0#link7)**
](https://www.mela.work/it/blog/rup-nuovo-codice-appalti-chi-%C3%A8-competenze-responsabilit%C3%A0#link10)**[4.Extended responsibilities of the RUP](https://www.mela.work/it/blog/rup-nuovo-codice-appalti-chi-%C3%A8-competenze-responsabilit%C3%A0#link10)**
1.Introduction:
1.1 Current regulatory context:
The current regulatory context for public contracts is constantly evolving, driven by the need for greater efficiency, transparency and security. The recent dgls 36/23 represents a major reform with a significant impact on several aspects. We have already covered the main updates introduced by the New Public Procurement Code, and today we will look in greater detail at one of the main innovations: what has changed in the role of the RUP, which has changed from Single Procedure Manager to Single Project Manager. This article explores the key aspects of this change.
It is important to note that the new Public Procurement Code forms part of a broader renewal, moving the RUP from a previously limited role to one of crucial importance. The focus is on improving the management of public resources, increasing transparency in decision-making processes and promoting greater efficiency in awarding public contracts.
Before examining the evolution of the RUP’s role in detail, let us first look at the main differences between the Single Procedure Manager and the Single Project Manager in the new Public Procurement Code.
1.2 Differences between the Single Procedure Manager and the Single Project Manager in the new Public Procurement Code:
1-Broader role and name:
-Old RUP: the role of the Single Procedure Manager was often associated with managing individual procedures
-New RUP (2023): changing the name to Single Project Manager highlights a broad change in perspective. The new RUP is no longer limited to managing individual procedures, but assumes responsibility for every stage of the project. The RUP therefore becomes the contract’s actual project manager.
It is also relevant to note that, under the new dgls 36/23, the RUP and the other figures involved in design are increasingly moving towards the use of case-specific digital tools (e.g.:BIM_building information modelling).
2-Extended responsibilities:
-Old RUP: traditionally involved from the conception of the tender through to contract award, the old RUP had a role largely confined to this stage.
-New RUP: the RUP’s responsibilities extend across every stage of the project, from programming and design through to award and execution. Its central role in the process is emphasised from the first act initiating the public intervention.
3-Early involvement:
-Old RUP: the RUP’s involvement could vary depending on the specific procedure.
-New RUP: the RUP must be appointed from the first act initiating the public intervention, highlighting the need for an early and influential presence.
4-Active participation in tender panels:
-the new RUP may be part of tender panels. This represents a significant expansion of its responsibilities, influencing decision-making and the awarding of public contracts.
In summary, under the new Public Procurement Code 2023, the RUP assumes a broader and more influential role than the former Single Procedure Manager. This reflects regulatory developments and the intention to improve public procurement management.
The evolution of the RUP’s role can therefore be summarised as follows:
The RUP, once merely responsible for procedures, becomes a key actor involved in every stage of the project. This evolution marks a turning point in the way public contracts are managed.
Having outlined the main innovations concerning the RUP under dgls 36/23 and the differences from the Single Procedure Manager, let us now examine this role in detail and see what the new Public Procurement Code says, focusing on:
Appointment and planning of the RUP;
Requirements, skills and duties;
Extended responsibilities;
Participation in tender panels.
2.Appointment and planning of the RUP (Single Project Manager):
The appointment of the RUP plays a crucial role in shaping a project’s outcome. Let us look at the appointment and planning dynamics, outlining the importance of a strategic appointment and a responsive approach to the project’s needs.
2.1 Appointment of the RUP (Single Project Manager): importance, transparency and efficiency
The appointment of the Single Project Manager (RUP) is a fundamental act under the new Public Procurement Code 2023. Unlike in the past, the new regulatory context emphasises the importance of a timely and strategic appointment. The choice of RUP is now part of the first act initiating the public intervention, often coinciding with the planning stage.
As stated in Article 15 of dgls 36/23, the appointment of the RUP (Single Project Manager) “is based on clear criteria of competence and impartiality. The Public Procurement Code 2023 establishes that the RUP may be appointed by contracting authorities and contracting entities, and may be selected from among fixed-term employees of the contracting authority or contracting entity, preferably serving in the organisational unit holding spending authority, who meet the requirements set out in Annex I.2 and have professional skills appropriate to the duties assigned to them, in compliance with their contractual classification and related duties. Contracting authorities and contracting entities that are not public administrations or public bodies shall identify, under their own rules, one or more persons to whom the RUP’s duties may be assigned, limited to compliance with the provisions of the Code to which they are subject. The office of RUP is mandatory and may not be refused. If the RUP is not appointed in the act initiating the public intervention, the role is performed by the manager of the organisational unit responsible for the intervention.”
The appointment stage therefore plays a crucial role in ensuring the proper conduct of the entire procurement process. Choosing a competent, impartial and appropriately trained person is essential to safeguarding the integrity of decision-making and compliance with current regulations. The timely appointment of the RUP supports strategic planning covering every project stage and demonstrates a clear intention to ensure maximum transparency, which is essential for building trust among all parties involved.
2.2 RUP planning: defining the framework for the project
RUP planning is the next critical step after appointment. Once designated, the Single Project Manager undertakes strategic planning covering every project stage. This process requires a thorough understanding of the public intervention’s objectives, available resources and deadlines.
RUP planning involves clearly defining the activities to be carried out during the different project stages. From programming and design through to award and execution, each stage requires particular attention and careful management. The RUP ensures that every activity is clearly assigned, establishing specific responsibilities for each stage and ensuring a fair distribution of the workload.
The appointment and planning of the RUP are two key stages in implementing the new Public Procurement Code 2023. These steps establish the basis for transparent and efficient application of public procurement regulations.
So what are the RUP’s requirements and skills under the new Public Procurement Code?
Let us take a look!
3.RUP requirements, skills and duties under the new Public Procurement Code 2023:
3.1 RUP requirements and skills under the new Public Procurement Code 2023:
In accordance with the new provisions of the Public Procurement Code 2023, the Single Project Manager (RUP) must have specific requirements and skills depending on the type of contract. Qualification requirements vary according to the nature of the works and supplies, following strict guidelines to ensure professionalism and efficiency.
Works and engineering and architectural services require specific technical skills and qualifications. Works contracts and concessions require experience proportionate to the value of the contract. Services and supplies require an appropriate qualification and continuous updating. Specific services may require additional qualifications. Complex works require experience, a master’s degree and project management skills.
Specific training is therefore essential.
The reform aims to ensure the RUP’s continuous development and appropriate qualification, improving efficiency and professionalism in the procurement process.
You can explore the RUP’s requirements and skills directly in Annex I.2 of the new Public Procurement Code (dgls 36/23)
And what are the RUP’s duties?
3.2 RUP duties: a central role in public procurement stages
The new Public Procurement Code 2023 gives the RUP a central role at every stage of the public contract. From coordinating design activities through to execution, the RUP performs a cross-functional role, ensuring a coordinated and integrated approach.
In accordance with the new regulations, the RUP is responsible for coordinating every stage of the public contract. In addition to supervising, the Single Project Manager acts as a point of reference for all parties involved. Integrated management of the stages reduces risks and improves the quality of the procurement process.
The RUP thus becomes the guarantor of transparency, efficiency and fairness in the supplier selection process. Its active participation at every stage highlights the significant change in its role, establishing a key figure in the reform of the Public Procurement Code 2023.
As stated in Article 6 of Annex I.2 to dgls 36/23:
The RUP coordinates the implementation process for the public intervention in compliance with the planned deadlines and costs, the required quality and scheduled maintenance. During execution, the RUP monitors, in particular, compliance with the rules protecting workers’ safety and health.
If you want to explore the RUP’s duties under the new Public Procurement Code in greater detail, they are set out in the same Article 6 of Annex I.2.
Extended responsibilities of the RUP:
As noted above, the RUP, once limited to managing individual procedures, now assumes extended responsibilities covering the project’s entire life cycle. This section examines the transformation from a mere procedure to complete management, highlighting the efficient distribution of responsibilities.
4.1 From a mere procedure to complete management:
The role of the Single Project Manager (RUP) has evolved significantly, changing from a mere procedure manager into a key actor in the overall management of the project. This transformation represents an important turning point in public procurement, allowing the RUP to exercise broader and more integrated control over the entire project life cycle.
4.2. Phase Manager: effective distribution of responsibilities
The introduction of the Phase Manager has created an efficient dynamic for distributing responsibilities. Each stage of the procurement process is now managed more specifically, allowing the RUP to delegate particular responsibilities and ensuring optimal management without overload. This approach aims to improve the smooth running of the overall process.
As stated in Article 15, paragraph 4 of dgls 36/23:
“Without prejudice to the single nature of the RUP, contracting authorities and contracting entities may identify organisational models providing for the appointment of a procedure manager for the programming, design and execution stages and a procedure manager for the award stage. The relevant responsibilities are divided according to the duties performed at each stage, without prejudice to the RUP’s supervisory, guidance and coordination functions.”
This approach aims to prevent overload and ensure optimal management of the individual project stages.
4.3 Support structure: optimising the management of complexity
Another important measure, intended to ensure efficient resource management and allow the RUP to focus on key decisions, is mentioned in point 6 of the same Article 15 of the new Public Procurement Code, which states:
“Contracting authorities and contracting entities may establish a support structure for the RUP, and may allocate financial resources not exceeding 1 per cent of the tender base amount for the RUP’s direct assignment of assistance engagements.”
This is an essential mechanism for addressing particular complexities.
In summary, the RUP may use Phase Managers and request a support structure. This will ensure optimal management of public contracts by allowing the Single Project Manager to focus on key decisions.
We are nearly at the end of this article, but before concluding, let us look at another major innovation affecting the RUP (Single Project Manager) under the new Public Procurement Code.
id="link1"
5.Participation in tender panels:
One of the new Code’s most significant innovations is the possibility for the RUP to sit on tender panels. This section examines the RUP’s key role on these panels and the expansion of its responsibilities, including the power to chair below-threshold contracts.
5.1 The RUP’s key role on tender panels:
The RUP’s participation in tender panels enables a more thorough assessment of tenders. Detailed knowledge of the subject matter of the contract translates into a greater ability to identify the most suitable offer.
The RUP’s active participation supports a more thorough assessment of tenders, promoting transparency and fairness in the selection process.
5.2 Broader responsibilities: chairing below-threshold contracts
Article 51 of dgls 36/23 states:
"Where contracts covered by this Part are awarded using the most economically advantageous tender criterion, the RUP may take part in the tender panel, including as chair."
It can therefore be said that, in addition to participation, the new Code gives the RUP the power to chair below-threshold contracts. This expansion of responsibilities emphasises the RUP’s leading role, not only as an evaluator but also as a leader in procurement decisions.
This represents a genuine turning point. The recognition emphasises the RUP’s leading role in ensuring fair and transparent contract distribution.
6.Conclusions:
In conclusion, we have seen how the RUP, once a marginal figure, has become a key protagonist in public procurement. Its extended role, active participation in tender panels and ability to chair in the cases described above place it at the centre of decision-making and efficient project management.
The regulatory context is constantly evolving, and the RUP’s role adapts accordingly. Exploring future prospects and possible developments is crucial to fully understanding the dynamic world of public procurement.
Stay informed and follow Mela to keep up to date!