Managing the costs of a non-digital construction site: who would have thought?

The cost of managing a construction site, rarely taken into account, inevitably affects a company's performance. The main items are: direct management costs (the time and other costs invested in management operations), which reach 140 euros per week for each construction site, and indirect management costs (managing decisions and risks). The conclusion is that the highest management cost is represented by delays in completing the work, and is directly proportional to the value of the entire construction site.

Managing construction site costs: what needs to be measured?

We are always talking about a digital construction site. Now let us look at the opposite and talk about an “analogue” construction site. So, let us examine the cost of managing a construction site without digital tools. Is it really that much? Yes, indeed: let us see why.

Managing a construction site means collecting information, cataloguing it correctly, combining it and extracting FIGURES and DECISIONS from it

To simplify, construction site costs are of 2 types:

I. The time spent collecting and managing information, and the cost of storing it

II. The hidden costs

I. What is the cost of collecting and storing information?

To calculate the costs, we consider 2 information management activities that are simple and essential for every construction site:

  1. What happens on site: tracking the history (including at least photos).
  2. The costs of staff, materials and external services

These are not the only processes for collecting and managing information from the construction site (safety, testing, etc.), but let us start here.

1. What happens on site: tracking the history with photos

a. Unnecessary site visits

As a business owner, it is essential to be informed about how construction sites are progressing, and photos can tell you more than a thousand words. But do you necessarily need to go to the construction site in person to do this?

Each site visit costs approximately 50 euros, broken down as follows:

  • The time spent travelling to the construction site
  • The travel cost of getting to the construction site (petrol if you used your car)

The alternative is to use the site manager's presence to collect photos and communicate from the construction site, involving the contractor only in the event of critical issues.

b. Transferring and organising photos

Once taken, the photos need to be saved in a secure, shared location for archiving.

  • Let us assume 15 minutes per week to transfer them from a smartphone to a PC, and around 30 minutes to catalogue the photos clearly and recognisably. The total is around 45 minutes. If this activity is carried out by the technical manager, it is worth approximately 29 euros.

WARNING! If the photos are not named so that they can be linked to a specific activity, this also affects costs in terms of the time spent “deciphering” them and possibly resolving errors. Excavations, bricks and pipes all look alike! It is difficult to identify, for example, the photo of the screed in flat 1 and that of flat 2.

c. Archiving photos so they become a company asset

If the photos remain on the computer of the person who downloaded them, two problems arise:

  1. It is difficult to share them and extract value from the history of the information;

  2. There is no redundancy in the archiving, and the risk of data loss therefore increases.

It is therefore advisable to use a shared company server or a cloud storage solution, whose cost is around 20 euros per month.

Cost of taking and archiving photos:

Almost 80 euros per week per construction site!

2. The costs of staff, materials and external services

a. Completing paper reports

Let us assume that, for each construction site, the following are completed:

  • 1 report per day for HOURS WORKED (5 minutes)
  • 1 report per week for MATERIALS (15 minutes)
  • 1 report per week for EXTERNAL SERVICES (5 minutes)

The time needed to complete the reports is therefore around 45 minutes and, if carried out by the site manager, amounts to around 26 euros per week for each construction site.

b. Delivering the reports to head office

Once a week, the reports must be taken to head office. The DDTs and any other invoices or accounting documents delivered on site must also be submitted with the reports. Taking the journey and the site manager's time into account, the assumed cost is 17.50 euros per week.

c. Transferring report data

To transfer the data to the internal accounting system, whether a management system or an Excel spreadsheet, we estimate around 5 minutes per report (for 5 reports, corresponding to the working days per week), which already amounts to 25 minutes of the accountant's time, plus another 5 minutes for storing the paper records. This brings the total to 12.50 euros.

Below are the hourly costs of the different professional roles.

Total weekly cost of managing the reports: approx. 56 euros

Total cost of the time spent managing information:

136.25 euros per week per construction site if highly efficient

II. Hidden costs. What are they and how are they calculated?

Hidden costs—difficult to measure and often non-linear—can be divided into two areas:

  1. Costs linked to slow information while the construction site is in progress
  2. Costs linked to a lack of information, especially after the construction site has been completed

How many days late do you find out the costs being incurred by the construction site? Or rather: how many weeks late??

In our interviews, all companies confirmed that they experienced a delay ranging from 15 DAYS to 1 MONTH

1. Costs linked to slow information

Slow acquisition of information is certainly the greatest cost linked to managing a construction site traditionally.

In fact, operational decisions are normally made without knowing whether they fall within the site budget. How can risks be avoided?

  1. Relying on experience
  2. Postponing important decisions

The consequence is that timescales become longer and you have to deal with the disappointment of clients who no longer want to absorb unforeseen costs.

But the real cost of all is that the construction site slows down. If you want to avoid making risky decisions and information circulates slowly, delays inevitably build up. This mechanism generates a cost directly proportional to the delay.

Assuming a construction site with a planned duration of 100 days

If the delivery delay is 10%, the costs of lost production will also tend to equal 10% of the total construction site costs. This does not even include any penalty costs!

This is the TRUE and significant COST of slow information

2. Costs linked to a lack of information

A lack of information is a rarer occurrence, because once the construction site has been completed, the likelihood of complaints is fairly low (and in any case the work is insured).

Since the company is primarily responsible for the quality of the work, it is advisable to create a quality track record, demonstrate it to clients, reassure them that everything was done properly and thereby gain their trust.

Documented work with all the information is preferable in any case, for at least 2 reasons:

1. The client is satisfied with the work carried out

2. The client will not make any claim

Did you know that these costs—as well as the headaches and wasted time spent on boring, unproductive activities—could be avoided by choosing digital tools?