Accounting register: what it is and how to complete it in 2023

Accounting register: what it is, how to complete it, who is responsible for preparing it and how digital tools can help. Everything you need to know about the document that summarises the project's entire accounts, with a template to use as an example.

Accounting register

The construction accounts consist of a series of technical and administrative documents and records relating to the supervision of the works. Their purpose is to record accurately all work that involves expenditure and therefore contributes to the total costs.

The project's entire accounting is summarised and collected in the accounting register. The document contains details of each item of work, with its contractual unit prices, in order to determine the progress of the works, in two respects:

  1. On the one hand, how much work has been carried out and what it consists of, together with its cost
  2. On the other, the amount earned to date by the contractor.

In this article, we will look at the purpose of the accounting register, who is responsible for preparing it and how this accounting document must be completed.

Accounting register: what it is

The accounting register is a document that summarises all the financial details of a project. The agreed contract prices are applied to each item of work carried out and recorded in the measurement book.

The accounting register is essential for monitoring and recording the progress of the works in its entirety, not only in terms of the quantity of work completed but also, as we have seen, in terms of the credit accrued by the contractor.

Accounting register: who is responsible for completing it

According to the Decree 7 March 2018, no. 49 of the Italian Ministry of Infrastructure and Transport, the works supervisor is the professional responsible for monitoring and recording the costs relating to the execution of the project, including the complete list of expenditure items for the work carried out. This is done by classifying and measuring the work performed, and then transferring the data from the surveys carried out to the accounting register.

It is therefore clear that the regularity and accuracy with which the register is completed are vital to the accounting of the project, since they form the basis for the content of two other accounting documents: the SAL — progress statement — and the final account.

The accounting register is the document essential to the progress of the works in which the project's entire accounting is summarised.

The works supervisor's responsibilities for the accounting register

Moreover, as reiterated by Annex II.14 to Legislative Decree 36/2023, the works supervisor controls expenditure on the project, ensuring that all accounting documents are completed accurately and promptly, at the same time as the relevant events occur. These are official documents used to ascertain and record events that generate expenditure on a project.

In particular, referring to Annex II.14 to Legislative Decree 36/2023, point 3 of Article 1: "The works supervisor is responsible for controlling expenditure relating to the execution of the project or works by completing the accounting documents accurately and promptly. These documents are public records for all legal purposes and are used to ascertain and record events that generate expenditure."

The works supervisor must classify and measure the work carried out, then transmit and record these measurements in the accounting register in order to monitor costs.

There is an important point to note, however. This process must be carried out at the same time as the works progress, to ensure that:

  • progress statements are issued within the deadlines set for payment of the initial instalments, for the purpose of issuing certificates for the payment of advances by the RUP;
  • the works proceed in a controlled manner and meet the authorised timescales and budgets.

In fact, the same Annex II.14 to Legislative Decree 36/2023, point 3 of Article 1, continues: "For this purpose, [the works supervisor] classifies and measures the work carried out, transfers the surveys performed to the accounting register and carries out the resulting calculations that make it possible to identify the progress of expenditure.

Under the principle of continuous accounting progress, the activities described above for ascertaining events that generate expenditure must be carried out at the same time as those events occur and must therefore proceed in parallel with execution. The works supervisor ascertains and records all events that generate expenditure at the same time as they occur."

The works supervisor must classify and measure the work carried out, then transfer and record it in the accounting register to monitor costs.

Accounting register: what it must contain

The accounting register must be numbered, stamped and signed by the parties involved to guarantee its authenticity and prevent fraudulent substitutions.

It contains a cover page with information about the project, the company involved and the number of pages. In detail, it must include:

  • Subject of the works
  • Registered name of the contracting company
  • Number of sheets making up the register

The internal pages of the register must contain transcriptions of the entries in the measurement books. In particular, under Article 14 of Ministerial Decree 49/2018, paragraph 1, point c), they must contain specific columns recording the unit price and the corresponding amount for each item of work.

The regulations also require the accounting register to include the deductions made by the works supervisor, together with the relevant explanations. It is important to pay attention to the contractor's claims, because when signing the final account, the contractor may not submit claims other than those already recorded in the accounting register, nor change their amount or subject matter.

Accounting register: how it must be completed

The accounting register is managed by the works supervisor and may be in paper or digital format. Its completion follows strict procedures to guarantee authenticity:

  1. The RUP — Sole Person Responsible for the Procedure — must sign both the cover page and every page.
  2. The pages must be numbered in advance and stamped in accordance with Article 2215 of the Italian Civil Code. ("Before being put into use, accounting books must be numbered consecutively on every page and, where stamping or authentication is required, each sheet must be stamped by the companies register office or a notary in accordance with the provisions of special laws. The register office or notary must state on the last page of the books the number of sheets they contain.")
  3. Data must be recorded in chronological order.
  4. The executing company must sign the register on each occasion when a progress statement is issued.

In special circumstances, the works supervisor may propose that the RUP divide the register into sections or by types of work, provided that all entries are kept in chronological order on every sheet.

The works supervisor is responsible for preparing and continuously updating the accounting register, as well as for its administrative and criminal liability.

Accounting register: how digital tools can make the process easier, faster and more effective

The accounting register is a genuine, accurate and timely record of what has been completed and how it was completed.

Accounting is closely linked to site supervision and control, ensuring that everything takes place within the established deadlines and helping to mitigate human errors caused by incorrect or incomplete transcriptions.

The tools we recommend for accounting are above all digital and mobile — because bulky, non-portable objects are not suitable for construction sites — and characterised by ease of use, designed first for fieldwork and then for office work.

Finally, they can collect data directly on site and present it immediately to all the parties involved.

With the Mela app, you can digitise the accounting register, the site diary, the measurement book and the accounting register, basing them on the project's bill of quantities and integrating them as required.

With Mela's mobile digital tools, you can monitor the project's accounts promptly and accurately, improving site productivity and reducing costs caused by inefficiency and delays.

The Mela app also provides a secure and reliable cloud archive that tracks every item of data and allows it to be shared with all the professionals involved.

Questions and answers

What is the accounting register?

The accounting register is the site document that summarises all the financial details of a project. The agreed contract prices are applied to each item of work carried out and recorded in the measurement book.

Who is responsible for preparing the accounting register?

The works supervisor is responsible for preparing the accounting register and must also have the document signed by all the project stakeholders, the executing company and the contracting authority.

Who signs the accounting register?

The accounting register — like the measurement book, the progress statements, the site diary and the final account — is signed by the works supervisor and the contractor.